5 Commissioning
03.04.2006
5 Commissioning
Preparation for use and commissioning of Synco™ 700 devices must be under-
taken by qualified staff who have been appropriately trained by SBT HVAC Prod-
ucts or their delegates.
5.1
Entering the commissioning mode
5.1.1
Entry on first startup
When supplying power to the bus operator for the first time, the
Language
menu ap-
pears. Here, the language required for operating the plant can be selected. Then, the
Commissioning
menu will appear.
The access level is set to “Password level”.
The bus operator unit is to be commissioned in accordance with the Installation Instruc-
tions G3113; they are enclosed with the RMZ792.
5.1.2
Entry from the main menu
The Commissioning menu is reached after selecting operating line
Commissioning
(ap-
pears only on the password level) and confirmation with the OK knob.
5.2
Leaving the password level
On completion of commissioning, select the user level (access level for the plant opera-
tor). To do this, proceed as follows:
1. Select the start page: Press the ESC button repeatedly until the start page reap-
pears.
2. Press the OK knob and the ESC button simultaneously. The
Access levels
menu
appears.
3. Press
the
OK
knob.
4. Select
the
User level
by turning the OK button and confirm by pressing the knob.
5. If required, enter the password needed for the user level.
6. Press the OK knob to confirm the password.