Commissioning the system
05.07.2007
Connect outputs
Connect the output for heat demand DC 0..10 V
Inform the central apartment unit that you want to use universal out-
put U of the RRV912 heating circuit controller as a DC 0..10 V heat
demand output:
Main menu > Commissioning > RF connections > Outputs >
Heat demand DC 0..10 V > Connect device:
Confirm subentry “Connect device“ by pressing the
Menu/ok
button.
To make the connection, you is prompted to press the binding button
on the device to be connected.
Select universal output U with the channel selection button (CH) on
the heating circuit controller. The LED of the selected channel blinks.
If the selected channel is not yet connected, the connection LED
flashes.
Now, press the multifunction button on the heating circuit controller.
The LED lights up green. When it starts blinking, you can release the
binding button.
A successful connection is shown on the display of the central apart-
ment unit and be confirmed with a beep. Close the binding process
by pressing the
Menu/ok
button.
Connect the heat demand relay
Inform the central apartment unit that you want to use a universal
relay output Qx of a heating circuit controller as a heat demand out-
put:
Main menu > Commissioning > RF connections > Outputs >
Heat demand relay
> Connect device:
Confirm subentry “Connect device“ by pressing the
Menu/ok
button.
To make the connection, you is prompted to press the binding button
on the device to be connected.
Select a universal relay output Qx with the channel selection button
(CH) on the heating circuit controller. The LED of the selected chan-
nel blinks. If the selected channel is not yet connected, the connec-
tion LED flashes.
Now, press the multifunction button on the heating circuit controller.
The LED lights up green. When it starts blinking, you can release the
binding button.
A successful connection is shown on the display of the central apart-
ment unit and be confirmed with a beep. Close the binding process
by pressing the
Menu/ok
button.
Содержание Synco 900
Страница 1: ...Synco 900 Mounting and commissioning Edition 2 0 Controller series B CE1C2707en 05 07 2007 ...
Страница 2: ......
Страница 84: ...84 88 Siemens Synco 900 CE1C2707en Building Technologies 05 07 2007 ...
Страница 85: ...85 88 Siemens Synco 900 CE1C2707en Building Technologies 05 07 2007 ...
Страница 86: ...86 88 Siemens Synco 900 CE1C2707en Building Technologies 05 07 2007 ...
Страница 87: ......