1.0 Introduction
Planned maintenance is recurring and must be performed at least every 12
months. Planned maintenance includes visual inspections, safety testing,
cleaning, and functional performance checks of the system and its equipment.
Print the maintenance report contained in the appendix, "Maintenance Report"
(page G-1). Enter the data in the report as the planned maintenance is
performed. A copy of the completed maintenance report must be provided to
the customer and to the regional service office, as appropriate to the region.
Some regions require planned maintenance more frequently. It is the
responsibility of the customer service engineer (CSE) to be aware of, and
adhere to, all local regulations regarding planned maintenance intervals for this
system and its equipment.
If a test fails on a system covered by a full service contract, repair the defect
and repeat the check. If the system passes the test after being repaired, record
that the system passed the test.
If a test fails on a system not covered by a full service contract, obtain approval
from the customer to repair the defect. Repeat the test on the repaired system,
and record that the system passed the test. If the customer does not want you
to repair the defect, record that the system failed the test, and note this failure
in the open issues section of the maintenance report.
2.0 Required Tools and Documents
Use the following tools to perform the procedures described in this chapter.
Standard field service tools
MO diskette
Electrical safety analyzer
Ground resistance meter
Transducer
The
Field Electrical Safety Test Procedure
(p/n 7482776), the
G50 and
G60 S Electrical Safety Test Limits
(p/n 7482784), and the
Field Electrical
Safety Test Report
(p/n 7482768) are used during the planned mainte-
nance procedure.
3.0 Required Materials
Transmission gel is required to perform the testing and maintenance specified
in this chapter.
Note:
Always keep a copy of completed maintenance reports for your own
records.
Содержание SONOLINE G50
Страница 4: ...Page iv 7482255 Rev 01 Siemens October 2002 G50 and G60 S Service Manual ...
Страница 10: ...Page x 7482255 Rev 01 Siemens October 2002 G50 and G60 S Service Manual ...
Страница 22: ...Page 12 of 12 7482255 Rev 01 Siemens October 2002 Mechanical and Electrical Specifications ...
Страница 140: ...Page 8 of 8 7482255 Rev 01 Siemens October 2002 Verifying the Operation of the Software ...
Страница 182: ...Page 42 of 42 7482255 Rev 01 Siemens October 2002 Service Screens and Menus Figure 8 32 Color Scale Pattern ...
Страница 190: ...Page 8 of 8 7482255 Rev 01 Siemens October 2002 Concluding the Maintenance ...
Страница 196: ...Page 2 of 2 7482255 Rev 01 Siemens October 2002 Figure B 1 Installation Report Form ...
Страница 214: ...Page 18 of 18 7482255 Rev 01 Siemens October 2002 G60 S Spare Parts Photographs ...
Страница 216: ...Page 2 of 2 7482255 Rev 01 Siemens October 2002 ...
Страница 222: ...Page 6 of 6 7482255 Rev 01 Siemens October 2002 ...
Страница 226: ...Page 4 of 4 7482255 Rev 01 Siemens October 2002 ...
Страница 228: ...Page 2 of 6 7482255 Rev 01 Siemens October 2002 This page intentionally left blank ...
Страница 234: ...Page 2 of 2 7482255 Rev 01 Siemens October 2002 ...