Operators Tools
7-38
7SJ63 Manual
C53000-G1140-C120-1
7.3
Control of Switchgear
A SIPROTEC
®
4 device 7SJ63 contains control functions that allow for opening and
closing of power system switching devices (i.e. circuit breakers). Local control is pos-
sible utilizing different elements of the 7SJ63. Breaker control from a remote location
is also possible using the SCADA interface or DIGSI
®
4. (Performing control functions
with a PC running DIGSI
®
4, connected to the front serial port, is considered a “re-
mote” operation for breaker control purposes.) Some control actions from a 7SJ63 in-
clude unsynchronized commands for circuit breakers, circuit switchers, ground switch-
es, etc., and stepping commands for increasing or decreasing transformer LTC steps.
Safety mechanisms in the command path ensure a command can only take place if
the check of previously defined safety criteria is concluded positively.
If a power system switching device has auxiliary contacts that indicate the position of
the device and these contacts are connected to the 7SJ63 and configured as double-
point indications then the switching device provides feedback indication that are mon-
itored for plausibility of control actions. If a switching device does not indicate either
the closed or open position, the display for the switching device indicates an unvalid
position in the 7SJ63. All subsequent control operations to the equipment are inter-
locked.
Control from a 7SJ63 to a power system equipment can originate from four sources:
−
Local operation using the operator control panel,
−
Binary inputs,
−
Remote operation using the SCADA interface,
−
Operation with a PC, via the operating interface and DIGSI
®
4.
Switching priority for the four command sources is set using the Switching Authority.
For Interlocked Switching, all programmed interlocking conditions are checked before
a control operation is performed. If one of the conditions is not met, then the command
is rejected and an error message is recorded and displayed. Fixed, predefined, stan-
dard interlocking features are implemented in the 7SJ63 and can be configured (acti-
vated) for the specific application. The following tests can be activated (on) or deacti-
vated (off) for a switching device:
•
Device Position (check SCHEDULED = ACTUAL comparison).
•
Substation controller, to be implemented with Version 4.2,
•
Zone controlled (Field interlocking e.g., logic in CFC),
•
Blocking by protection (control operations blocked by protective functions),
•
Double operation (blocking of multiple control operations),
•
Switching authority (Local/Remote),
www
. ElectricalPartManuals
. com
Содержание siprotec 7SJ63
Страница 16: ...xiv 7SJ63 Instruction Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...
Страница 28: ...Introduction 1 12 7SJ63 Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...
Страница 112: ...SIPROTEC 4 Devices 4 38 7SJ63 Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...
Страница 346: ...Functions 6 182 7SJ63 Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...
Страница 494: ...Technical Data 10 48 7SJ63 Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...
Страница 604: ...Index Index 6 7SJ63 Instruction Manual C53000 G1140 C120 1 w w w E l e c t r i c a l P a r t M a n u a l s c o m ...