Mounting and Commissioning
3.2 Checking Connections
SIPROTEC, 7SD610, Manual
C53000-G1176-C145-6, Release date 02.2011
293
3.2.3
Checking the System Connections
WARNING!
Warning of dangerous voltages
Non-observance of the following measures can result in death, personal injury or substantial property damage.
Therefore, only qualified people who are familiar with and adhere to the safety procedures and precautionary
measures shall perform the inspection steps.
Caution!
Be careful when operating the device on a battery charger without a battery
Non-observance of the following measure can lead to unusually high voltages and consequently, the destruc-
tion of the device.
Do not operate the device on a battery charger without a connected battery. (For limit values see also Technical
Data, Section 4.1).
Before the device is energized for the first time, it should be in the final operating environment for at least 2
hours to equalize the temperature, to minimize humidity and avoid condensation. Connections are checked
with the device at its final location. The plant must first be switched off and earthed.
Connection examples for current transformer connections are provided in Appendix A.3. Please observe the
plant diagrams, too.
Proceed as follows in order to check the system connections:
• Protective switches for the power supply and the measured voltages must be switched off.
• Check the continuity of all current and voltage transformer connections against the system and connection
diagrams:
– Are the current transformers earthed properly?
– Are the polarities of the current transformers the same?
– Is the phase relationship of the current transformers correct?
– Are the voltage transformers earthed properly (if used)?
– Are the polarities of the voltage transformers correct (if used)?
– Is the phase relationship of the voltage transformers correct (if used)?
– Is the polarity for current input
I
4
correct (if used)?
– Is the polarity for voltage input U
4
correct (if used, e.g. with broken delta winding)?
• Check the functions of all test switches that are installed for the purposes of secondary testing and isolation
of the device. Of particular importance are test switches in current transformer circuits. Be sure these switch-
es short-circuit the current transformers when they are in the „test mode“.
Содержание SIPROTEC 7SD610
Страница 16: ...Contents SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 16 ...
Страница 267: ...Functions 2 18 Command Processing SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 267 ...
Страница 268: ...Functions 2 18 Command Processing SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 268 ...
Страница 428: ...Appendix A 10 Measured Values SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 428 ...
Страница 430: ...Literature SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 430 ...
Страница 442: ...Glossary SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 442 ...
Страница 448: ...Index SIPROTEC 7SD610 Manual C53000 G1176 C145 6 Release date 02 2011 448 ...