Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
307
Drive commissioning (SINAMICS)
9
9.1
Requirements
9.1.1
Basic requirements
The following basic requirements must be fulfilled for the commissioning of SINAMICS S120.
●
The electronic power supply of PG/PC, SINUMERIK 840Di sl and SINAMICS S120 is
switched on.
●
The mechanical and electrical elements of the SINAMICS drives are set up and
connected correctly, including DRIVE CliQ connections.
References:
SINAMICS S120, Commissioning Manual, Chapter "Preparations for Commissioning"
●
The SINAMICS STARTER drive commissioning tool is installed on the PG/PC. Version:
At least V4.0
●
PG/PC and SINUMERIK 840Di sl communication via Ethernet.
The Ethernet interface of the PG/PC must be connected to the Ethernet 1 interface of the
PCU for this, and the Ethernet communication must be parameterized. See Chapter "PLC
●
SINUMERIK 840Di sl and SINAMICS S120 communication via PROFIBUS.
The PROFIBUS interface (X101) of the MCI board must be connected to the PROFIBUS
interface of SINAMICS S120, and the PROFIBUS communication must be parameterized.
See Chapter "PROFIBUS DP communication" (Page 229).
3&8
;
;
(WKHUQHW
FRPSDQ\QHWZRUN
Содержание SINUMERIK 840Di sl
Страница 118: ...Configuration 3 3 Connection overview Manual 118 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 148: ...Power On and Power Up 5 7 License management Manual 148 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 186: ...PLC commissioning 6 8 Load configuration in PG PLC STEP 7 Manual 186 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 344: ...Drive commissioning SINAMICS 9 5 Basic principles Manual 344 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 624: ...Glossary Manual 624 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...