Hierarchy folder "Equipment module"
Several equipment modules such as a dosing or bottling machine can be defined in a unit.
Equipment phases such as heating, cooling, ventilating or emptying can be created for the
equipment modules.
7.1.3.8
Assigning the "Process cell", "Unit" or "Equipment phase" object type
To identify the BATCH hierarchy, each hierarchy folder is explicitly assigned the object type
"Process cell", "Unit", or "Equipment phase". Depending on the object type, other BATCH
attributes can then be set.
After creating a new hierarchy folder, one of the object types "process cell", "unit", "equipment
phase" or "neutral" is automatically assigned depending on the position. You can change the
object type assigned to a hierarchy folder as follows:
Procedure in the SIMATIC Manager
1. Select the hierarchy folder in the Plant view.
2. Select the menu command Edit > Object properties.
3. Switch to the "ISA-88 type definition" tab.
4. Set the required type (process cell, unit, or equipment module) of the hierarchy folder for
the "Object Type". If you select the "<neutral>" object type, the BATCH hierarchy will be
deactivated again for this folder.
5. Confirm with "OK".
Result: The graphic display of the hierarchy folder matches the selected object type.
Neutral folder
The "<neutral>" object type deactivates the BATCH hierarchy for the "process cell" object. The
lower-level BATCH hierarchy folders retain their object type but are no longer relevant for the
SIMATIC BATCH configuration. In "Object type", the nested hierarchy folders no longer
relevant for SIMATIC BATCH are displayed in round brackets, for example: (unit).
7.1.3.9
Specifying predecessors for a unit
Introduction
In the object properties of the "Unit" hierarchy folder, you can select a different unit of the same
project, or of a different project as successor for each unit. This prevents units that have no
connection in the plant structure from being selected during recipe creation.
You can also enter several units as successors, for example, as a preliminary selection and
then select the required successor in a master recipe.
You can also specify the predecessor of a unit defined as a successor as the next successor.
Engineering
7.1 Basic engineering for PCS 7
SIMATIC BATCH V8.2
138
Operating Manual, 02/2016, A5E35958174-AA
Содержание SIMATIC BATCH
Страница 30: ...Security information SIMATIC BATCH V8 2 30 Operating Manual 02 2016 A5E35958174 AA ...
Страница 135: ...Example Engineering 7 1 Basic engineering for PCS 7 SIMATIC BATCH V8 2 Operating Manual 02 2016 A5E35958174 AA 135 ...
Страница 403: ...BATCH Control Center 9 8 Batch control SIMATIC BATCH V8 2 Operating Manual 02 2016 A5E35958174 AA 403 ...
Страница 584: ...BATCH Recipe Editor 10 5 Other functions SIMATIC BATCH V8 2 584 Operating Manual 02 2016 A5E35958174 AA ...
Страница 722: ...Appendix 13 4 Command line parameters for BatchCC SIMATIC BATCH V8 2 722 Operating Manual 02 2016 A5E35958174 AA ...
Страница 1158: ...Index SIMATIC BATCH V8 2 1158 Operating Manual 02 2016 A5E35958174 AA ...