Installation and mounting
5.5 Setting up the charging station
SICHARGE D
Operating Instructions, 02/2021, 8EM5907-0AA00-1AA7.01
59
5.5.2
Positioning the charging station
To set up the charging station at the site, you need to lift the charging station from the
transport pallet using either a crane or a forklift (see section Transport and storage
(Page 40)). Then transport the charging station to the prepared base area. Lifting and
positioning with a crane is recommended. If crane lugs are needed, they can be specified and
ordered in the configurator.
Lifting the charging station from the load carrier
To lift the charging station from the load carrier, proceed as follows:
1.
Open the device door, remove the cable gland plate below the connection bars on the
circuit breaker and close the door.
2.
Repeat this step on the back of the device if you want to connect dispensers to the charging
station.
3.
Procedure with crane or forklift
–
Using a crane (recommended):
Mount the orderable crane lugs at the four corners of the enclosure frame on the roof.
When using your own crane lugs, ensure that they have an M12 thread that is 25 to
30 mm long and are suitable for the weight of the charging station. Then place the
hoist (see section 4.1) into the four crane lugs.
–
Using a forklift:
Drive the forks from the front or from behind under the bottom of the cabinet until the
forks protrude on the other side. Pay attention to the center of gravity of the device.
4.
Loosen the screws between the charging station and load carrier.
5.
Lift the charging station vertically.