11.6.7 Heating/cooling ch'over relay
If the H/C-signal is not to be sent to the bus but rather to a relay output to e.g.
switch a valve or to be routed to a non-communicative device, the H/C changeover
relay can be configured accordingly.
Main menu > Commissioning > Extra configuration > Heating/cooling ch'over
Operating line
Area
Factory setting
Heating/cooling changeover
relay
---, N.Q1, N.Q2,…/
---
The current state of the changeover relay can be queried:
Main menu > Heating/cooling ch'over
Operating line
Current state
Heating/cooling changeover
relay
"Off": Cooling / "On": Heating
During wiring test, the H/C changeover relay can be switched directly.
Main menu > Commissioning > Wiring test > Outputs
Operating line
Comments
Heating/cooling changeover
relay
"Off": Cooling / "On": Heating
11.6.8 Troubleshooting
The controller continues to apply the last received value if in a 2-pipe system the
changeover signal "Heating/cooling" is not on the bus. If there has never been a
signal, "Heating" is used as the default value.
No.
Text
Effect
5801 H/C
changeover
signal failure
Non-urgent message; must not be
acknowledged
The fault message "> 1 H/C changeover signal" is sent, if, in a 2-pipe system an
H/C changeover input heating/cooling is configured by date or Operating mode
selector and a changeover signal in one of the zones is received by another device
on the bus.
No.
Text
Effect
5802 >1
Heating/cooling
changeover signal
Non-urgent message; must be acknowledged
Configuration
Display values
Wiring test
Behavior
Fault status message
Behavior
Fault status message