![Siemens FDCIO223 Скачать руководство пользователя страница 57](http://html.mh-extra.com/html/siemens/fdcio223/fdcio223_technical-manual_377133057.webp)
Commissioning
Calibrating the control line
6
57 | 72
Building Technologies
009122_h_en_--
Fire Safety
2016-05-04
6 Commissioning
The device is commissioned via the control panel. The exact procedure is
described in the control panel documentation.
NOTICE
Before commissioning the device, check that the configuration of the
inputs/outputs corresponds to the circuit.
Conduct a performance check once commissioning is complete.
Measure the current at the activated outputs.
If the input/output module is to be used for control purposes, the control lines will
need to be calibrated during commissioning.
6.1 Calibrating the control line
The input/output module must be connected correctly (inputs/outputs and
power supply).
The detector line must have been commissioned.
The input/output module must be correctly configured.
The relay must not be triggered during calibration. This is especially important
in the case of inverse controls (normal position = triggered)! Consequently,
control must be activated for calibration in the case of inverse controls!
1. Press the push button (3) on the input/output module. See the chapter
The control lines will then be calibrated. Duration: approx. 4 s.
2. Check that calibration has been performed successfully.
Once calibration has been successfully completed, the input/output module
runs in normal operation.
If the calibrated resistance is outside the tolerance range, an error is indicated.
The control line will be recalibrated whenever the push button is pressed.
The line must be recalibrated with each new configuration.