7 | Installation
64/174
8DJH • Installation and Operating Instructions • Version 11 • 500-8384.9
7.13 Installing the top pressure absorber unit (IAC up to 21 kA)
Tab. 36:
Versions of top pressure absorber units
Top pressure absorber unit with-
out low-voltage compartment
Top pressure absorber unit with
low-voltage compartment
Top pressure absorber unit for me-
tering panel
Panels in free-standing arrangement (except metering panels)
Metering panels in wall-standing and
free-standing arrangement
1
Front cover
4
Absorber collar
2
Base with pressure absorber
5
Lateral part
3
Pressure relief duct
6
Low-voltage compartment (example)
7.13.1 Pressure absorber top unit with low-voltage compartment
If a low-voltage compartment must be mounted on the panels, then the low-voltage
compartment replaces the retaining bracket, the front cover and the lateral part on the
corresponding panel.
1. Remove the transport eyes and transport blocks [
Page 73, "Joining the panels"].
2. Install the low-voltage compartment [
Page 87, "Installing the low-voltage
3. In the following assembly operations, bolt the front cover of the adjacent panel and the
absorber collar together with the low-voltage compartment.
Fig. 51:
Pressure absorber top unit with low-
voltage compartment (example)
1
Pressure relief duct
2
Absorber collar
3
Front cover
4
Low-voltage compartment