COMMISSIONING
6
65
8020065-ZLP4/2017-08-10|SICK
Subject to change without notice
O P E R A T I N G I N S T R U C T I O N S | Master Data Analyzer
6.6
Performing a test run
Finish commissioning the system by performing a test run. The test run must make sure
that all components of the Master Data Analyzer are working correctly and that they are
delivering plausible measured values.
Performing a test run
Test the measurement accuracy of the Master Data Analyzer using a test object.
▸
Place the test object on the inside the measurement field on the glass panel.
▸
Move the measurement gantry over the test object.
▸
Rotate the test object in different directions and perform a measurement in each
position.
Displaying measurement results
All measurement results are listed on the display.
▸
Compare the recorded measured values with the defined measured values.
▸
If a valid bar code is read with the hand-held scanner this will also be displayed in the
list of measured values.
What to do if no dimensions are displayed
▸
Ensure that nothing is permanently in the way of the beam path of the light grids.
▸
Check for a
force shunt
in the system. No parts are permitted between the glass panel
and housing.
Checking data output
Check to see whether the measurement results have been correctly transmitted to the
customer system with the configured connection settings.