O P E R A T I N G I N S T R U C T I O N S | DUSTHUNTER SP100 Ex-3K
Subject to change without notice
12
MAINTENANCE
12.6.8
Replacing the hood
Replacement criterion: In case of damage.
Ex-condition:
Replacement can be carried out in the Ex-area when the absence
of a potentially explosive atmosphere has been verified with a gas
warning device.
Work steps:
1
Disconnect the entire device (control unit and sender/receiver unit) from the power
supply.
2
Disconnect the potential equalization line, if necessary.
3
Loosen the flange screws. Remove the sender/receiver unit from the duct. Allow to cool
down, if necessary.
4
Place the enclosure rear side of the sender/receiver unit on a flat surface.
5
Switch off purge gas supply, if necessary.
6
Loosen both screws (
à
) (SW 7) of the hood (
). Remove the
hood.
7
Fit the new hood and fasten it again with the two screws (torque 2 Nm)
8
Switch on the purge gas supply.
9
Fit the sender/receiver unit on the duct flange (torque 20 Nm).
10
Connect the potential equalization line.
11
Put the complete device back into operation (switch on voltage and check measured and
status values).
12.6.9
Replacing the copper seal of the non-return valve
Replacement criterion: In case of damage.
Ex-condition:
Replacement can be carried out in the Ex-area when the absence
of an explosive atmosphere has been verified with a gas warning
device.
Note
Depending on the design conditions on site, the seals can be
replaced without removing the sender/receiver unit from the duct.
In this case, work steps 2, 3, 4, 11 and 12 are not necessary.
Work steps:
1
Disconnect the entire device (control unit and sender/receiver unit) from the power
supply.
2
Disconnect the potential equalization line, if necessary.
3
Loosen the flange screws and remove the sender/receiver unit from the duct and allow it
to cool down, if necessary.
4
Place the enclosure rear side of the sender/receiver unit on a flat surface.
5
Switch off the purge gas supply.
6
Detach the purge air hose from the non-return valve.
7
Unscrew the non-return valve with a wrench (SW 22), then unscrew the reduction piece
(SW 24) and separate these components if necessary.
8
Screw reduction piece (
) back in with new seal (
) and, whilst
centering the sealing ring at the same time, tighten with 30 Nm..
9
Screw in the non-return valve (
) with new seal (
) and tighten
with 20 Nm.
10
Fit the purge gas hose and switch on the purge gas supply.
11
Fit the sender/receiver unit on the duct flange (torque 20 Nm).
12
Connect the potential equalization line.
13
Put the complete device back into operation (switch on voltage and check measured and
status values).