Installation
FLOWSIC100 Flare · Addendum to Operating Instructions · 8025365/V1-0/2020-05 · © SICK Engineering GmbH
31
4.3
Fitting the spool piece (option)
The spool piece must be mounted in the pipeline so that the arrow marking on it corre
-
sponds to the flow direction.
The flow is output by the measuring system as a positive value when master and slave of
the sender/receiver units for the cross-duct versions are installed according to Operating
Instructions FLOWSIC100 Flare, Figure 2.
Required fitting work
▸
Position the spool piece at the desired section of the pipeline using the hoist.
▸
After attaching the flange bolts, but before tightening, check the correct seating and
alignment of the flange seal.
▸
Align the spool piece so that the offset between inlet pipe, spool piece and outlet pipe is
minimized.
▸
Insert the remaining fixing screws and tighten the nuts crosswise. The applied torque
must not be lower than specified in the project planning.
▸
Install the pressure measurement line between the pressure tapping point (option) and
the pressure sensor (option).
▸
Perform a leak tightness check with suitable means after completion of the installation
work,
WARNING:
Hazard due to size and mass of the spool piece
▸
Observe the transport information on
!