Switching on sequence
Commissioning information
It is mandatory to adhere to the described switching on sequence.
In case of failures during commissioning, please refer to section “"Malfunctions" (
94).“
Switch the control system on:
•
Switch on the mains voltage, the control unit is ready for operation after about 1 s.
The control systems acts in accordance with the parameterized specifications
(signals at the digital inputs). The current operating status or a status message
are shown on the display.