SHANGHAI SERMATEC ENERGY TECHNOLOGY CO.,LTD
- 27 -
connection of PE line.
Warning
When wiring, make sure that there is no dangerous voltage at the
connection point.
4.7.8 Screw tightening torque
Query table of screw tightening torque
4.7.9 Inspection after installation
•
The energy storage device shall be inspected after installation
:
•
The equipment shall be placed and installed in a reasonable
position to meet the requirements of safe distance
;
•
The primary wiring is correct, the lower ground wire is well
connected with the grounding grid, and the construction unit is
required to test the grounding resistance value
;
•
Compare the factory main wiring diagram with the actual wiring
on site to see if there is any difference, and judge whether the
difference will affect the safe operation of the energy storage system.
Notes
All wiring is connected to the terminal from the outside through
the wire hole at the bottom of the energy storage device. After
wiring, please seal the wire hole with fireproof mud.
NO.
Type
Thread diameter
(
mm
)
Torsional
moment
(
N
·
m
)
1
Expansion screw
M10
16.4
2
screw
M8
12
3
screw
M4
2.4