Page 22 of 28
Doc. 6001072
Rev B
3. LIB Control
1. Single Unit Installations:
Connect the 4 twisted pair cable from the Ovation controller to TB1
on the connector board in the first LIB housing (see Figure 15).
Multiple Unit Installations:
Connect the 4 twisted pair cable from the Ovation controller to
TB1 on the MUI in the first LIB housing (see Figure 15).
2.
Connect all LIBs in the housing using the short 8-conductor cables with RJ45 connectors
(provided with the LIBs). Connect them from J1 (OUT) of one LIB to J2 (IN) of the next LIB.
3.
Repeat step 2 until all LIBs in the housing are connected.
4. For Multiple LIB Housings:
connect a 4 twisted pair cable from TB5 on the MUI in the first
housing to TB1 on the MUI in the next housing.
5.
Continue until all LIB housings are connected. After you have finished connections, apply
power. When the controller and LIBs are powered up, the POWER indicator will light on all the
LIBs in the stack (see Figure 14).
Figure 15. Connector Board and MUI Board Connections.