Overcurrent Elements 

Page 4 of 7 

20120723 

Step 9 

Set the 

Winding 2 Phase TOC Time Dial

51P2TD = __________________ 

For this exercise, set the time dial to 3 to provide time coordination with downstream devices. You can 
determine the time dial setting based on a fault coordination study. 

Step 10 

Verify that the following settings are at the default values: 

51P2RS = Y 

51P2TC = 1 

Step 11 

Save your settings, and then send them to the relay. 

Hands-On Activity 2: Validate Overcurrent Elements 

In this hands-on activity, you will validate the phase and neutral instantaneous overcurrent elements and 
the phase time-overcurrent elements. 

Validation Functional Description 

Figure 4 illustrates the location of Fault F1. The relay should operate when the fault magnitude exceeds 
the overcurrent relay setting and the time-delay elements time out. 

 

Figure 4  Overcurrent Validation Fault Location 

Содержание SEL-387A

Страница 1: ...instantaneous or definite time elements are available for overcurrent protection breaker failure protection overcurrent phase selection for targeting transformer backup protection and so on Two levels...

Страница 2: ...Element Settings Step 2 Determine the Winding 1 Max Phase Time Overcurrent Trip Level setting 51P1P ________________ The transformer maximum expected load equals MVA 1000 kV 3 Set the 51P1 pickup to...

Страница 3: ...5 Verify that the Neutral Inst Overcurrent Trip Delay 50NN1D is set at minimum value of 0 50 Step 6 Select Group 1 Set 1 Winding 2 Elements Figure 3 Phase Time Overcurrent Element Settings Step 7 Det...

Страница 4: ...default values 51P2RS Y 51P2TC 1 Step 11 Save your settings and then send them to the relay Hands On Activity 2 Validate Overcurrent Elements In this hands on activity you will validate the phase and...

Страница 5: ...le Relay Word bit asserts Step 1 Reset relay targets by pushing the TARGET RESET pushbutton located on the relay front panel Step 2 Clear the Sequential Events Recorder SER entries You can perform thi...

Страница 6: ...minals to simulate faults as indicated in Table 1 Step 1 Calculate the expected operate time using the equations from Figure 5 and record your answers in Table 2 Figure 5 Time Overcurrent Operation Eq...

Страница 7: ...rt command or the ACSELERATOR QuickSet HMI Step 3 After the instructor applies the fault current use the TARn serial port command n the Relay Word bit for the element under test or the ACSELERATOR Qui...

Отзывы: