Commissioning
76 / 105
ASD 531, Technical description, T 140 416 en
7.3.1
Commissioning procedure
The following illustrates the commissioning workflow for commissioning.
Fig. 42 Commissioning workflow
7.3.2
Setting the alarm threshold without “ASD Pipeflow” calculation
The following describes the procedure for setting the ASD 531 to one of the switch positions with fixed parameters
A/1
to
CC
.
Example
: The ASD 531 is to respond in compliance with EN 54-20, Class B. The sampling pipe is U-shaped with 3 sampling
holes per sampling branch. According to Sec. 4.4.4.1 switch position
B/6
is to be selected.
Measure
Indicator
Procedure / remarks
(1)
Turn rotary switch “
Class
” to position
“
B
”
--
•
Response behaviour compliant with EN 54-20,
Class
B
(2)
Turn rotary switch “
Holes
” to position
“
6
”
--
•
Total sampling holes set to
6
(2 sampling branches each with 3 sampling holes)
Notice
If there is a false or invalid entry (e.g. EN-Class A with 9 holes), LEDs “
Class
” and ”
Holes
”, begin to flash after
a delay time. After a second delay time the ASD triggers a fault.
Point of departure: tube system(s) mounted and connected to
ASD. Smoke sensor(s) deployed in the ASD.
Switch setting defined acc. to tube system (e.g.
), or
specification acc. to ASD
know after calculation.
B/6
“
”
“
”
PipeFlow
Switch on supply voltage (FACP). The fan accelerates stepwise
to ist defined speed (takes about 100 s). The next process can
nevertheless be performed immediately.
no
yes
. 7.3.2
Workflow Sec
Alarm threshold
calculated
with “ASD ”
Pipeflow
?
Commissioning workflow
Select required switch position for operation acc. to
Sec. 4.3.1.1.
. 7.3.6
Workflow Sec
. 7.3.4
Workflow Sec
After switching on, a
perform initial reset
minimum waiting time of 2 min
System in operation; commissioning ended
Select required switch setting for the airflow tolerance
and delay time acc. to Sec. 7.2.1.2.
Workflow Sec. 7.3.3
Select required switch position for operation acc. to
”
“
Sec. 4.4.4.1 (e.g.
)
B/6
.