Figure 27: Earth cables inlet
Operation sequence:
•
Remove the bottom plate.
•
Insert the cable lugs.
•
Route cables through the plate holes.
•
Re-position and fasten the bottom plate.
•
Completion of the cable lug (tighten the internal nut)
•
Connect of the ferrules to the DC.X2 terminal board
•
Close the unused cable lugs.
6.4.3. AC cables connection
For the technical data related to the connectable cables, their maximum cross-section and the type of cable
lug, please refer to 12.8. The AC module may have one or two AC output terminal boards, based on the
number of available DC sections (1 or 2). The AC module may be connected to a single- or double-
secondary transformer.
Inverter
AC Outputs
X2 Terminal
board
X2B Terminal
board
Phase
Sequence
Transformer
Connection
SUNWAY TG
610 1000V TE
1
DC Module
converter
output
Not present
Irrelevant
Irrelevant
SUNWAY TG
750 1500V TE
1
SUNWAY TG
1200 1000V
TE
2
DC1 Module
converter
output
Module
converter
output DC2
Irrelevant
Connect to
terminal X2-1
(X2-2, X2-3) the