SINUS PENTA
MODULAR INVERTERS
ASSEMBLY INSTRUCTIONS
15/
47
2.3.
Internal Wiring for Modular Inverters S75 - S80
Modular inverters S75 and S80 use both parallel-connected inverter modules and power supply modules.
To obtain parallel-connection, inverter modules equipped with splitter boards are required.
The following links are required:
N. 2 power connections with 60*10mm copper bar between the power supply units and the inverter modules
in order to deliver DC voltage.
N. 12 links with 9-pole shielded cable (S80) or N. 11 links with 9-pole shielded cable (S75) for the analog
measures.
Type of cable: shielded cable
N. of conductors: 9
Diameter of each conductor: AWG20÷24 (0.6÷0.22mm
2
)
Connectors: 9-pole SUB-D female connectors
Connections within the cable:
Connector
SUB-D
Female
connector
SUB-D
Female
connector
pin
1
→
1
pin
2
→
2
pin
3
→
3
pin
4
→
4
pin
5
→
5
pin
6
→
6
pin
7
→
7
pin
8
→
8
pin
9
→
9
Connections required:
-
from control unit to power supply unit 1 (control signals for power supply unit 1)
-
from power supply unit 1 to power supply unit 2 (control signals for power supply unit 2)
-
S80 only: from power supply unit 2 to power supply unit 3 (control signals for power supply unit 3)
-
from control unit to splitter board in inverter module U1 (phase U control signals)
-
from control unit to splitter board in inverter module V1 (phase V control signals)
-
from control unit to splitter board in inverter module W1 (phase W control signals)
-
from splitter board in inverter module U1 to inverter leg U1 (phase U1 control signals)
-
from splitter board in inverter module V1 to inverter leg V1 (phase V1 control signals)
-
from splitter board in inverter module W1 to inverter leg W1 (phase W1 control signals)
-
from splitter board in inverter module U1 to inverter leg U2 (phase U2 control signals)
-
from splitter board in inverter module V1 to inverter leg V2 (phase V2 control signals)
-
from splitter board in inverter module W1 to inverter leg W2 (phase W2 control signals)