Confidential
3
.
Installing the Product
English 8/2019. Rev 0.0
27
3.8
Preparation Stage—Visual Inspection
CAUTION
If any defects are found during the inspection, contact the SAMSUNG SDI customer service
department.
3.8.1
Inspection of the Rack Frame
After transporting the rack frame to the installation location, check for:
Structural damage
Paint peeling
Damaged or protruding screws.
After completion, install or package the rack for protection during storage.
3.8.2
Inspection of the Modules
After transporting the modules to the installation location, check for:
Physical damage to the exterior
Damaged or protruding screws
Proper voltage and internal impedance of the battery modules using the battery tester.
Table 3-8: Module Voltage and Internal Impedance
No.
Items
Value
1
Voltage Check
28.712 ~ 29.104V
2
Internal Impedance Check
3.0 ~ 4.3 mΩ
After completion, install the battery module in the previously installed rack or return the battery module to
its original packing for protection during storage.
3.8.3
Inspecting the SMU
After transporting the SMU to its installation location, check for:
Physical damage
Paint peeling
Damaged or protruding screws.
After completion, install the SMU in the previously installed rack or return the SMU to its original packing for
protection during storage.
Содержание 136S
Страница 1: ...Confidential English 8 2019 Rev 0 0 LIB System for UPS Installation Manual 136S ...
Страница 4: ...Confidential English 8 2019 Rev 0 0 ...
Страница 10: ...Important Safety Instructions Confidential vi English 8 2019 Rev 0 0 ...
Страница 18: ...Confidential Table of Contents viii English 8 2019 Rev 0 0 ...
Страница 149: ...Confidential 3 Installing the Product English 8 2019 Rev 0 0 131 Figure 3 164 Cell Information ...
Страница 153: ...Confidential Memo ...
Страница 154: ...Confidential Memo ...
Страница 155: ...Confidential Memo ...
Страница 156: ...www SamsungSDI com ...