Installing the Product
English 8/2019. Rev 0.0
21
Table 3-1: Estimated time for installation (based on 136S 3P installation)
No.
Step
Estimated Time
(HH:MM)
Aggregated Time
(HH:MM)
1
Unpacking
00:30
00:30
2
Inspection
01:00
01:30
3
Rack Anchoring
04:00
05:30
4
Rack Installation
Battery Module
00:20
05:50
SMU
00:10
06:00
SMPS Assembly
00:10
06:10
Rack Fuse Assembly
00:30
06:40
Busbar
01:00
07:40
Signal Cables
00:20
08:00
Power and Control Cables
00:20
08:20
AC Input Installation
00:20
08:40
Cable Installation
00:10
08:50
BMS Configuration
00:10
09:00
Содержание 136S
Страница 1: ...Confidential English 8 2019 Rev 0 0 LIB System for UPS Installation Manual 136S ...
Страница 4: ...Confidential English 8 2019 Rev 0 0 ...
Страница 10: ...Important Safety Instructions Confidential vi English 8 2019 Rev 0 0 ...
Страница 18: ...Confidential Table of Contents viii English 8 2019 Rev 0 0 ...
Страница 149: ...Confidential 3 Installing the Product English 8 2019 Rev 0 0 131 Figure 3 164 Cell Information ...
Страница 153: ...Confidential Memo ...
Страница 154: ...Confidential Memo ...
Страница 155: ...Confidential Memo ...
Страница 156: ...www SamsungSDI com ...