Confidential
3
.
Installing the Product
English 8/2019. Rev 0.0
85
3.10.6
Module and SMU Signal Cable Connection
Connect the signal cables for SMU and Module BMS’s for each module.
NOTICE
Use the proper signal cables as specified by the part numbers below.
WARNING
Rack BMS / Module BMS Damage
Do not insert both ends of the signal cable WIRE ASSY MODULE TO MODULE #1 or WIRE ASSY
MODULE TO MODULE #2 into the same Battery Module.
1.
Connect the signal cable “WIRE ASSY RACK TO MODULE” between the SMU “MODULE” connector and
Module #1 “Right Connector”.
Figure 3-90: SMU to Module #1 Signal Cable
Содержание 136S
Страница 1: ...Confidential English 8 2019 Rev 0 0 LIB System for UPS Installation Manual 136S ...
Страница 4: ...Confidential English 8 2019 Rev 0 0 ...
Страница 10: ...Important Safety Instructions Confidential vi English 8 2019 Rev 0 0 ...
Страница 18: ...Confidential Table of Contents viii English 8 2019 Rev 0 0 ...
Страница 149: ...Confidential 3 Installing the Product English 8 2019 Rev 0 0 131 Figure 3 164 Cell Information ...
Страница 153: ...Confidential Memo ...
Страница 154: ...Confidential Memo ...
Страница 155: ...Confidential Memo ...
Страница 156: ...www SamsungSDI com ...