Use of the product
06/11/2020
582127110-2B1000-indD-EN.docx
28
9
Use of the product
9.1
User settings
Wet Cup
Before commissioning, fill the wet cup halfway with lubricant "T".
The wetting cup nut must be tightened moderately. Overtightening
quickly damages the gland packing. A wrench is supplied to allow
proper tightening.
Tightening of the Wet Cup
Verify cup is filled with lubricant "T",
Run the pump, then tighten the cup after 10 minutes, again
after 1 hour, then after1 day of operation,
In the event of a leak, the cup must be tightened.
Tightening procedure
Depressurize the Air motor (see depressurization procedure),
Depressure the product circuit (see depressurization
procedure),
Tighten the cup, clean it and fill it with lubricant "T",
Close the pump purge circuits,
Open the Air motor air valve.