Table of Contents
SafetyLink Anchor Handbook Extract - FrogLink - Version 08.17
Page 6 of 8
FROGLINK ANCHOR UNIT
Product Code: FROGL001
INSTALLATION: TO THE SURFACE OF A METAL ROOF
1.
Place the FrogLink on the surface of the roof sheet running parallel with the sheets profile in the
required location. FrogLink anchor is recommended to be installed in the top section of the profile
aligned with the fall of the roof, when this cannot be achieved the FrogLink can be installed into the
pan, be sure not to create an area where leaves or debris can collect.
2.
Drill Seven (7) x 8mm holes into the roof sheets through the locating holes on the FrogLink.
3.
Secure the FrogLink to the roof by riveting through the holes in the FrogLink Anchor and the roof
sheet using 8mm Gesipa rivets.
Use QR code over for video installation.
4.
The FrogLink Anchor Point is now ready for use, giving you an anchor point to attach to while
installing the next FrogLink.
Live Load on Anchors:
The FrogLink anchor is best suited to roof pitches up to 30 degrees. For over 30 degrees FrogLinks should
be used in conjunction with other access methods to ensure no live loading. Note: These anchors are not
abseil anchors and therefore if they are subjected to a live load this may trigger the energy absorbing
regions.
DURING INSTALLATION YOU MUST BE SAFE AT ALL TIMES.
IF ANY DOUBT EXISTS WITH THE STRENGTH OF THE STRUCTURE OR ROOF SHEETS AN ENGINEER
SHOULD MAKE THE ASSESSMENT.
INSTALLATION MUST BE CARRIED OUT BY, OR UNDER THE SUPERVISION OF A COMPETENT
PERSON.