
Engineering manual - SAB 193-233-283 S A-frame (including ATEX)
164/175
008831 en 2022.02
15.5
Start-up
The plant can now be put into operation, See
Operating manual
.
After five hours of operation, the alignment between motor and compressor must be checked
again while the compressor is still warm. Before letting the plant start to work, activate the
emergency stop and dismount the main fuses to ensure that the motor does not start
unintentionally.
Important!
Note the procedures for reducing the evaporating pressure.
15.6
Commissioning set
As impurities in the piping are released during start-up of the plant, experience has shown that
both the suction filter and oil filter will clog up quickly. Consequently, a commissioning set is de-
livered with the compressor unit. This set includes a new filter and the necessary O-rings and
gaskets for the oil filter and suction filter. The spare parts included in the set are marked in the
parts list with a *.
Содержание SAB 193 S
Страница 1: ...SAB 193 233 283 S A frame including ATEX Screw compressor units Engineering manual EN...
Страница 2: ......