Synergy Display Replacement • 7
7.
Use a pair of small needle-nose pliers to disconnect the
3-Pin Display
Power Cable
from the power connector on the
Function Switch
Board
.
8.
Remove the retaining screws from each corner of the display and put
them in a safe place. You will need them to install the new display.
9.
Carefully remove the display from the inside of the control panel.
Installing the Synergy Display
To install the new display, you will need a pair of small needle-nose pliers and a
Phillips screw driver.
1.
Use a pair of small needle-nose pliers to install the
3-Pin Display
Power Connector Cap
(
30-00104
) into the power connector on the
Function Switch Board
. The new display does not require a separate
power connector.
Warning Hazardous Voltage
— You must install the 3-Pin
Power Connector Cap to protect the live power pins in the
connector. Failure to do so could result in personal injury or
damage to equipment.
2.
Carefully install the new display into the hole that the old display was
removed from.
3.
Install the retaining screws into each corner of the display. Do not
over-tighten the screws.
4.
Connect the
15-Pin Data Cable
to the data connector on the display.
Ensure that the orientation of the connector, with relation to pin 1, is
the same as it was when the cable was connected to the old display.
Caution
— You must install the 15-Pin Data Cable onto the new display
in the same orientation as it was removed from the old display. Installing
the cable incorrectly could damage the display and the switcher.