MegaDySC Dynamic Voltage Sag Corrector

Applying Power

• After installation make certain there are no metal filings or any conductive debris in or on any components inside 

the cabinets.

• Verify MegaDySC system voltage rating matches AC source voltage.
• Verify all input and output terminations including Grounding have been completed and properly tightened.
• Replace all covers. Close and lock all cabinet and switchboard doors.
• Allow commissioning technicians to complete connections and initial checks.
• Apply power from the upstream branch protection device when instructed to do so by the commissioning 

technicians.

• After commissioning, follow instructions on the Automatic Bypass switchboard to put the system into Normal 

mode. The load is now being protected by the MegaDySC. The display should show “OK” in the upper left corner

• Cycling input power in the sequence OFF--ON--OFF--ON within a one minute period will cause a ‘Limit Cycle 

Timeout’ alarm. In such case sag correction will be disabled for one minute, after which the alarm will 
automatically reset. 

• Push Button ‘Close CBI’ is disabled for one minute after CBI is opened for any reason.

ATTENTION: 

The MegaDySC system must be commissioned by factory-trained engineers. Do not energize the MegaDySC system until instructed to do so by 

commissioning engineers. If the Automatic Bypass switchboard must be installed and energized before commissioning, follow instructions below 

Figure 5

.

ATTENTION: 

The MegaDySC and (optional) ER cabinets are interlocked. Opening cabinet doors while in the MegaDySC ‘normal’ mode will cause immediate 

automatic bypass operation and subsequent loss of voltage sag protection while in ‘maintenance bypass’ mode. Automatic Bypass switchboard cabinet doors are 
not interlocked and should be kept locked to avoid exposure to dangerous voltages.

ATTENTION: 

 For operation, display screen, and maintenance information, see MegaDySC Dynamic Voltage Sag Corrector User Manual, 

Publication 

1608M-UM005.

Содержание Allen-Bradley MegaDySC 1608M Series

Страница 1: ...equipment The MegaDySC system provides instantaneous dynamic sag correction to help your equipment ride through these common events It connects normal utility power directly to the load until a volta...

Страница 2: ...ncati nella sezione Altre risorse riguardanti l installazione la configurazione ed il funzionamento dell apparecchiatura Gli utenti devono leggere e comprendere le istruzioni di installazione e cablag...

Страница 3: ...nment freeofconductive contaminants Avoid installing the MegaDySC system directly near heat emitting equipment such as ovens heaters or furnaces Ambient temperature must not exceed 40 C 104 F Do not o...

Страница 4: ...mic Voltage Sag Corrector SystemLayout Figure 1 Standard Run SR System Layout 12 7 21 5 1 29 723 2 81 7 6 5 48 5 25 167 7 21 6 7 2 5 167 7 21 5 7 6 5 1 5 1 6 12 7 21 6 3 66 167 7 21 5 48 5 25 5 48 5 2...

Страница 5: ...ic Voltage Sag Corrector Figure 2 Extended Run ER System Layout 12 7 21 5 1 29 723 2 81 7 6 5 48 5 25 167 7 21 5 7 1 581 5 7 6 5 48 5 25 5 1 5 48 5 25 02 8 12 7 21 6 5 1 6 7 2 5 167 7 21 167 7 21 6 3...

Страница 6: ...must be to the right of the Automatic Bypass section when viewed from the front of the system The DySC 400A Module MegaDySC section is shipped separately from the Automatic Bypass switchboard The Meg...

Страница 7: ...t This cable harness is routed through two large holes one in the ABP cabinet and one in the MegaDySC cabinet at the bottom front of the cabinets The harness is plugged into the associated terminal bl...

Страница 8: ...the control cable harness from the lower front switchboard pan into the MegaDySC section through the matching holes in the lower front side panels Install the 3 5 snap in grommet so that it protrudes...

Страница 9: ...21 25 87 7 1387 287387 5 029 723 3 1 72 5 1 25 381 175 5 21 6 520 520 5 5 520 7 7 51 7 27720 175 5 21 25 87 7 1387 287387 6 7 6 0 6 723 3 1 37 7 225 3 1 6 127 5 029 87 7 1387 0 0 3 5 3 6 287387 72 35...

Страница 10: ...tor Communication on page 12 MegaDySCSystemInterconnectionsChecklist Connect the Automatic Bypass ABP Switchboard to MegaDySC ground cable to the vertical strut in the MegaDySC cabinet at the location...

Страница 11: ...open removing power from the MegaDySC cabinet voltage sag correction will then be disabled This feature can be used as an Emergency Power Off EPO function for the MegaDySC cabinet Power to the output...

Страница 12: ...pass switchboard and is pre wired to monitor the MegaDySC input and output voltages The i Sense Ethernet and Modem communication ports are internally connected to the RJ45 and RJ11 jacks respectively...

Страница 13: ...ut power in the sequence OFF ON OFF ON within a one minute period will cause a Limit Cycle Timeout alarm In such case sag correction will be disabled for one minute after which the alarm will automati...

Страница 14: ...t rated for DC loads max allowable 2 DC loading Voltage Waveform Sine wave Voltage Sag Correction Times Single Event 3 phase 87 to 50 voltage remaining 5 s All three phases to zero voltage remaining 5...

Страница 15: ...Heat Loss Btu h Efficiency 480V SR 2421 8270 99 480V ER 2852 9740 99 380V SR 2321 7925 99 380V ER 2624 8960 99 3 wire 4 wire SR ER MegaDySC MegaDySC ER Weight Automatic Bypass Switchboard Weight Total...

Страница 16: ...We Doing form at http literature rockwellautomation com idc groups literature documents du ra du002_ en e pdf Technical Support Center Knowledgebase Articles How to Videos FAQs Chat User Forums and P...

Отзывы: