Maintenance
Required Tools
• Torque wrench: 0…48 lb•ft (0…65 N•m)
• Sockets: 3/8 in., 7/16 in., 9/16 in.
• Ratchet handle and extension
• Wrenches: 7/16 in., 1/2 in., 9/16 in.
• Feeler gauges: 0.050 in. (1.3 mm), 0.080 in. (2 mm), 0.020 in. (0.5 mm)
• Flat-blade screwdriver
• Nyogel 759G Lubricant (Allen-Bradley part no. 80158-357-51)
• MV Door Key
• Allen Key
• Speed Wrench
• Cart-latch key
• Earthing Switch operating tool
Maintenance of Industrial
Control Equipment
Periodic Inspection
Industrial control equipment should be inspected periodically. Inspection
intervals should be based on environmental and operating conditions and
adjusted as indicated by experience. An initial inspection within 3...4 months
after installation is suggested. See National Electrical Manufacturers
Association NEMA) Standard No. ICS 1.3, Preventive Maintenance of
Industrial Control and Systems Equipment, for general guidelines for setting-
up a periodic maintenance program. Some specific guidelines for Rockwell
Automation products are listed below.
ATTENTION:
Servicing energized Industrial Control Equipment can be
hazardous. Severe injury or death can result from electrical shock, bump, or
unintended actuation of controlled equipment. Recommended practice is to
disconnect and lockout control equipment from power sources, and release
stored energy, if present. Refer to National Fire Protection Association
Standard No. NFPA70E, Part II and (as applicable) OSHA rules for Control of
Hazardous Energy Sources (Lockout/Tagout) and OSHA Electrical Safety
Related Work Practices for safety related work practices, including procedural
requirements for lockout-tagout, and appropriate work practices, personnel
qualifications and training requirements where it is not feasible to de-
energize and lockout or tagout electric circuits and equipment before
working on or near exposed circuit parts.
Содержание Allen-Bradley 7712
Страница 6: ...6 Rockwell Automation Publication 7712 UM001D EN P October 2017 Table of Contents Notes ...
Страница 10: ...10 Rockwell Automation Publication 7712 UM001D EN P October 2017 Preface Notes ...
Страница 14: ...14 Rockwell Automation Publication 7712 UM001D EN P October 2017 Chapter 1 General Information Notes ...
Страница 24: ...24 Rockwell Automation Publication 7712 UM001D EN P October 2017 Chapter 3 Start up Procedure ...
Страница 25: ...Rockwell Automation Publication 7712 UM001D EN P October 2017 25 Start up Procedure Chapter 3 ...
Страница 26: ...26 Rockwell Automation Publication 7712 UM001D EN P October 2017 Chapter 3 Start up Procedure ...
Страница 36: ...36 Rockwell Automation Publication 7712 UM001D EN P October 2017 Chapter 4 Equipment Operation Notes ...
Страница 58: ...58 Rockwell Automation Publication 7712 UM001D EN P October 2017 Chapter 5 Maintenance Notes ...
Страница 73: ......