1 Introduction
MANUAL TME400-VCF · EN08 · July, 01
st
2021
29
1.4.2.4.
Installation
Note
Installations disturbing the gas flow directly upstream of the turbine meter
must be avoided
(see DVGW guideline G 492 II and PTGB guideline G 13).
An inlet pipe of at least 2 x DN is required upstream from the turbine meter TME400.
The inlet pipe must be designed as a straight pipe section with the same nominal di-
ameter as the meter. With heavy upstream pertubations, installation of straighteners
is recommended (refer to the table on the next page). A pipe or bend with the nomi-
nal diameter of the meter having a total length of 2 x DN must be arranged down-
stream from the meter.
Temperature measuring devices must be installed at a distance of at least 1 x DN or
at least 300 mm with nominal diameters
DN 300.
If there is pertubation (e.g. a gas pressure control device) upstream from the inlet
pipe, a perforated plate straightener is also necessary. Perforated plate straighteners
according to ISO 5167-1 or the type RMG LP-35, which cause a pressure loss by a
factor of 2.5 in comparison with the standard straightener, can be used.
Recommended installation with straightener
Perforated plate straightener LP 35
1
Perforated plate straightener
•
The opening angle of the reducing or expansion pieces which are installed up-
stream from the TME400 turbine meter must not be more than 30°.
Note
If necessary, a screen must be installed before the inlet pipe of the meter for
protection of the turbine meter from foreign objects which may be present in
the gas flow. The screen can be, for example, a perforated plate/filter of
0.15 mm.
Содержание TME400
Страница 1: ...Operating Manual Turbine Meter TME400 VC VCF Issued July 01st 2021 Version 08 Firmware 1 06 ...
Страница 50: ...2 Installation MANUAL TME400 VCF EN08 July 01st 2021 44 Ex version ...
Страница 51: ...2 Installation MANUAL TME400 VCF EN08 July 01st 2021 45 Ex version with current module ...
Страница 52: ...2 Installation MANUAL TME400 VCF EN08 July 01st 2021 46 Non Ex version ...
Страница 130: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 124 ...
Страница 131: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 125 ...
Страница 132: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 126 ...
Страница 133: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 127 ...
Страница 134: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 128 ...
Страница 135: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 129 ...
Страница 136: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 130 ...
Страница 137: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 131 ...
Страница 138: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 132 ...
Страница 139: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 133 ...
Страница 140: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 134 ...
Страница 141: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 135 ...
Страница 142: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 136 ...
Страница 143: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 137 ...
Страница 144: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 138 ...
Страница 145: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 139 ...
Страница 146: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 140 ...
Страница 147: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 141 ...
Страница 148: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 142 ...
Страница 149: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 143 ...
Страница 150: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 144 ...
Страница 151: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 145 ...
Страница 152: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 146 ...
Страница 153: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 147 ...
Страница 154: ...APPENDIX MANUAL TME400 VCF EN08 July 01st 2021 148 ...
Страница 155: ...MANUAL TME400 VCF EN08 July 01st 2021 149 ...