INSTALLATION
Electrical
Control Box (Optional)
C
A
B
A Cylinder Port A
B Cylinder Port B
C Air Supply Inlet (Back Side)
1 Install control box and remote disconnect
approximately 54 in (1372 mm) above floor level
2 Provide 110 VAC power to the control box Wire
3 Connect optional proximity switch wires to the
terminal blocks per the wiring diagram provided,
see
"SlideAir Control Box Wiring Diagram" on
Power/Startup
1 Turn power on to the control box
2 Turn on air supply
3 Press the open button; the curtain will slide to the
storage position
Junction Box (Optional)
1 Install junction box and suggested remote disconnect
(supplied by others) in an area that can be accessed
for maintenance
2 Bring signal wires from the machine controller to the
terminal blocks provided The signal wires type will
need to match the type of valve (supplied) (110 VAC
or 24 VDC) Connect the optional proximity switch
wires to the appropriate terminal blocks Wire per
instructions provided, see
or
Box Wiring Diagram – 24 VDC" on page 14
Figure 5