8
Pub. No. 1327 — January 2014
RITE-HITE
®
VBR-600 DOK-LOK
®
Installation Manual
INSTALLATION CONT.
Control Box Installation Guidelines -
Temperature Controlled Applications.
a. Conduit should be routed to enter through the
bottom or side of the enclosure. A drip leg may
be needed if the conduit could fill with water.
b. Seal the conduit in any location where the
conduit transitions temperature zones that may
produce condensation.
c. Spacers should be installed between the
enclosure and the wall to provide tempature
insulation and air flow.
13.
Connect wiring as indicated by the Electrical
Schematic and Wiring Diagram. See figures 7 & 8
or figures 9 & 10.
14.
To complete installation see page 12, Fill and Bleed
Hydraulic System section.
• The control box and all wiring should be
installed by a qualified electrician in
accordance with all national and local
electrical codes.
• If rigid conduit is installed, bonding must be
maintained between conduit connections by
using ground bushings and a jumper wire.