Rinnai
19
SS850 Freestanding IM
PLINTH INSTALLATION
Mounting area and mounting plate
1.
Mark the flue centre on the floor.
2.
Place the base mount panel on the floor and line up with the centre marks, and mark the area for power and
gas to enter. The alternate power and gas options shown in the cube installation also apply here.
3.
Check there is sufficient timber under the screw mounting holes to provide adequate retention. If necessary,
underfloor blocking may be required. A minimum of four screws, two front and back, are required.
Prepare Services
For best results the gas and power can be supplied
through the plinth and into the base of the fire. The
power will need to be hard wired.
Bring enough cable through the floor to reach at least
100 mm above the top of the plinth. Bring the gas
supply through to within approximately 50 mm of the
top of the plinth, flare the pipe, and fit the supplied
flexi tube. This should be leak tested now as access
through the back panel is limited once the fire is
installed. The alternative is to drill a hole in the back
of the fire for the gas supply and to remove the notch
for the power cord.
Base mount plate
Base cover plate
Underside cover x2
Side panel x2
Back outer panel
Tube connector
Flexi tube
Support rail x2
Screw pack (36 screws)
Front panel
55 mm min.
distance from wall
150 Min
400 mm
368 mm
50 min
Flue
centre
Power
supply entry
Gas
supply entry
Fire
Footprint
Approx. 400 mm
Ap
pr
ox
. 2
70
m
m
INSTALLATION