background image

Series GU/F 

Page 

10

 

 
 

 

9530-020-en 

Revision 15 

TM 10477

 

Edition    05/2022 

6.2  Sizing of the outlet line 

 

Outlet  lines  are  to  be  sized  so  that  reliable 
functioning of the valve is ensured under all 
expected operating conditions.  

The  medium  is  to  be  discharged  so  that  there  is  no 
risk  to  people  and  the  environment.  The  statutory 
provisions  (e.g.  accident  prevention  regulations,  and 
the equivalents of the German Pollution Control Act or 
the  German  Clean  Air  Code)  as  well  as  local 
regulations (works standards) are to be observed.  

  There must be no possibility of the overflow valves 

becoming ineffective due to shut-off elements. 

 
 

6.2.1  Admissible back pressure 

 

The  outlet  line  must  never  be  smaller  than  the 
nominal diameter of the overflow valve outlet.  

  The  admissible  back  pressure  in  the  valve  outlet 

must not be exceeded  in order to prevent destruc-
tion  of  the  bellows  or  a  reduction  in  the  discharge 
capacity. 

The  overflow  valve  test  certificate  and  the  brochure 
contain information of the manufacturer on admissible 
back pressures. 
 
 

6.2.2  Drainage of condensate 

Lay  horizontal  pipes  with  a  gradient  away  from  the 
valve  so that the liquid medium cannot accumulate in 
the  valve  body  and  that,  in  the  case  of  gases,  no 
condensate collects in the body. 

If  outlet  lines  are  laid  with  a  geodetic  level  difference 
(e.g.  for  vapours  or  gases  with  a  90°  vertical  upright 
pipe  bend  out  of  the  valve),  the  bend  must  not  be 
located directly downstream of the valve. 

A  horizontal  pipe  section  with  a  gradient  must  firstly 
be installed downstream of the valve. 

A draining facility must be provided at the lowest point 
in  the  pipe.  This  opening  for  the  drainage  of  conden-
sate must be lower than the flow chamber of the body. 

 

 

 

Fig. 3 

 
 

6.2.3  Discharge conditions and reaction 

forces 

At low temperatures: 

 

Outlet  lines  must  be  protected  against 
freezing.  This  applies  in  particular  if  gas 
cooling  as  a  result  of  expansion  is  to  be 
expected or lines are laid outdoors. 

 

With crystallising media: 

 

In  the  case  of  media  which  tend  to 
crystallise,  solidify  or  stick,  appropriate 
action  must  be  taken  to  ensure  that  the 
solidification  process  cannot  take  place  in 
the  inlet  or  outlet  lines  or  in  the  body  (e.g. 
installed  rupture  disc,  insulation,  heating). 
e.g. installed rupture disc, insulation, heating 

 

With gassing media: 

In  the  case  of  gassing  or  vaporising  liquids, 
adequately dimensioned flashtraps must be located in 
the direct vicinity of the valve. 
 

Reaction forces during discharge 

 

The  pipes  and  their  holders  are  to  be 
dimensioned so that their weight forces and 
the  reaction  forces  and  thermal  loads 
produced  during  discharge  can  be  safely 
absorbed. 

Instructions  for  calculating  the  reaction  forces  are 
contained  in  the  Richter  publication  "Plan  and  install 
overflow valves". 
 
 

 

6.3  Valve connecting dimensions 

The 

main  dimensions 

are 

contained  in  the 

dimensional drawing in 

Section 10.5

 

Содержание GU/F Series

Страница 1: ...ore transport installation operation and maintenance Subject to change without notice Reproduction is generally permitted with indication of the source Richter Chemie Technik GmbH 9530 020 en Revision...

Страница 2: ...caps and gaskets 11 6 5 Direction of flow and installation position 11 6 6 Grounding 11 6 7 Installation 11 6 8 Gas tight design Option 11 6 9 Signal transmitter Option 12 7 Operation 13 7 1 Initial c...

Страница 3: ...sed face ANSI ISA 75 08 09 2004 class 300 with flanges ASME B16 5 Class 300 raised face Materials Body material Ductile cast iron EN JS 1049 ASTM A395 Lining material PTFE PFA on request non conductiv...

Страница 4: ...quence The tightening torques for pipe screws and body screws mentioned must not be exceeded For an exception see Section 8 Flange connection valve pipe is leaking The following tightening torques are...

Страница 5: ...emperature diagram 2014 68 EU PED AD2000 DIN EN 16668 metal seat seat plug PTFE carbon ASME B 16 42 metal seat seat plug PTFE carbon DIN EN ISO 15848 1 certificate valid from 29 C to 180 C The diagram...

Страница 6: ...Directive DGRL They have a corrosion resistant plastic lining Solids can lead to increased wear damage to sealing surfaces or to a reduction in the service life of the valve The overflow valves are se...

Страница 7: ...the valve must be completely filled with medium at all times or else a potentially explosive atmosphere must be excluded by superimposing a layer of inert gas b Discharges outside the valve At the poi...

Страница 8: ...ns Never transport the valve using the lifting lever 238 See sectional drawings in Section 10 Transport the valve upright in a box or on a pallet on a soft surface and deposit gently on flat ground Di...

Страница 9: ...medium residues in the valve Separate valve materials plastics metals etc and dispose of them in accordance with the local regulations 6 Installation The installation conditions to the AD 2000 Code A...

Страница 10: ...ases with a 90 vertical upright pipe bend out of the valve the bend must not be located directly downstream of the valve A horizontal pipe section with a gradient must firstly be installed downstream...

Страница 11: ...ews using tooth lock washers One pipe screw per flange is underlaid with toothed disks At the customer s request a setscrew M6 with a hex nut and washer will be provided at each flange as an additiona...

Страница 12: ...monitoring Glue in stem extension 805 e g Loctite 638 and secure with a hex nut 920 4 The support lower part 542 is screwed on instead of the cap nut 927 1 Insert the O ring 400 3 Mount support upper...

Страница 13: ...valve make sure that all the appropriate steps as described in Section 6 1 to 6 7 and Section 7 1 are repeated 7 4 Improper operation and their consequences Fig 7 The test pressure checked by the man...

Страница 14: ...is necessary Medium is escaping at the bonnet Have the hex socket screws 914 1 not been tightened If after tightening the screws tightness still cannot be restored either the plastic lining or the be...

Страница 15: ...e material after cleaning Wear the prescribed protective clothing Overflow valves which have been cleaned with water or other media must be dried before re assembly of the parts and installation of th...

Страница 16: ...nd screw completely onto the thread of the bellows hand tight Counter the bellows 206 on the reinforced section with a pair of pliers Undo the hex socket screws 914 1 Centre the spring bonnet 513 with...

Страница 17: ...s bubble tight 10 Drawings 10 1 Legend 100 Body 117 thrust flange 124 pressure ring 204 plug 205 seat 206 bellows 237 lifting aid 238 lifting lever 305 bearing guide 306 stem guide 307 1 guide bush 30...

Страница 18: ...Series GU F Page 18 9530 020 en Revision 15 TM 10477 Edition 05 2022 10 2 Sectional drawing...

Страница 19: ...Series GU F Page 19 9530 020 en Revision 15 TM 10477 Edition 05 2022 10 3 Views View X Detail Y upper spring plate Detail Z lower spring plate...

Страница 20: ...drilled to ASME B16 5 Class 150 Flanges acc to ASME B16 5 Class 150 or 300 raised face Nominal size DIN EN 558 1 series 1 ANSI ISA 75 08 01 Class 150 ANSI ISA 75 08 01 Class 300 d0 H H1 L L L mm inch...

Страница 21: ......

Страница 22: ......

Страница 23: ......

Страница 24: ...om T V S d Industrie Service GmbH Voraussetzung f r die G ltigkeit der Herstellererkl rung ist das Beachten und Einhalten der Betriebsanleitung meet the requirement of the leakage rate La S 10 4 mg s...

Страница 25: ...ls The laws are such as the Health and Safety at Work Act ArbSt ttV the Ordinance on Harzadous Substances GefStoffV BIOSTOFFV the procedures for the prevention of accidents as well as regulations to e...

Страница 26: ...tamination of the pumps valves and component sent in for repair On the basis of this information for the contractor is it possible to meet the necessary preventive action during the execution of the r...

Страница 27: ...ch cleaning method radioactive3 1 if no then forward to D other pollutant 2 Aggregates which are contaminated with microbiological or explosive substances are only accepted with documented evidence of...

Страница 28: ...ai Info idexcorp com Internet www richter ct com Richter Pumps Valves Inc 406 State Street Cedar Falls 50613 IA USA Tel 1 319 268 8038 Fax 1 319 273 8157 Email RichterCedarFalls Info idexcorp com Inte...

Отзывы: