COMMISSIONING
49
INSTALLATION CHECKLIST
Prior to handover, complete the final check list:
1. System is installed as per the installation instructions ............................................................................ [ ]
2. Potable water is connected, turned on and solar storage tank is filled ................................................... [ ]
3. All mechanical fixings are secured .......................................................................................................... [ ]
4. Collectors have correct kick (12-15 mm per collector) ............................................................................ [ ]
5. Protective plastic film removed from tank (if fitted) ................................................................................. [ ]
6. Covers removed from collectors .............................................................................................................. [ ]
7. Pipe, conduit penetrations through the roof have been sealed correctly ................................................ [ ]
8. Roof tiles put back into position ............................................................................................................... [ ]
9. Roof flashing watertight ........................................................................................................................... [ ]
10. System checked for water leaks and pipe connections are correctly tightened ...................................... [ ]
11. Cold and hot water piping checked for water leaks ................................................................................. [ ]
12. Drain pipes free of any obstruction .......................................................................................................... [ ]
13. All pipe work clipped where necessary ................................................................................................... [ ]
14. Electrical power to the booster is switched on (if required) ..................................................................... [ ]
15. Operation of booster checked ................................................................................................................. [ ]
16. Air bled from taps .................................................................................................................................... [ ]
17. Owner has been instructed on use and has been given this booklet ...................................................... [ ]