COMMISSIONING
56
MULTIPAK – OPTIONAL CIRCULATING PUMP SUCTION STRAINER CLEANING
1.
Turn Off the power supply to the circulating pump. Isolate the pump upstream valve.
2.
Remove the pump upstream strainer assembly. Clean and refit.
3.
Re-instate the pump upstream valves to open position.
4.
Follow the secondary pump commissioning start-up instructions 7, 8 and 9 as stated before.
5.
Re-instate the pump power supply.
Basic Instruction for inline wet rotor Circulating Pump;
Motor shaft shall be Horizontal. Never operate dry. Loop cable down on exiting
terminal box as shown. Bleed pump; Confirm rotation. Free shaft assembly, if
necessary; Power supply timer is required to turn off pump automatically at least
four (4) times daily for 5 minutes; Clean pump suction strainer regularly.
Pump Upstream
Isolation Valve
Check Valve
Strainer
Содержание Multipak MPE02
Страница 44: ...44 MULTIPAK INTERNAL MPI02 MPI06 GENERAL ARRANGEMENT ...
Страница 45: ...45 MULTIPAK EXTERNAL MPE02 MPE06 GENERAL ARRANGEMENT ...
Страница 57: ...57 This page is intentionally blank ...
Страница 58: ...58 This page is intentionally blank ...
Страница 59: ...59 This page is intentionally blank ...