STAIR RAIL
INSTRUCTIONS
RAILING DYNAMICS, INC.
FOR hOMe, FOR LIFe™
135 STeeLmAnvILLe RoAd
egg HARboR TownSHIp, nJ 08234
TeL: (877) 420-7245
FAx: (866) 277-5160
e-mAIL: [email protected]
URL: www.RdIRAIL.com
NOTE: Check with your local building code office for design load requirements for
guard rails and bottom space requirements. All supporting structures should be built
in accordance with applicable building codes.
1.
prepare all posts and mounting surfaces
before installation.
2.
Temporarily secure a plank on the noses
of the stairs between the posts onto
which you are installing the stair rail.
(Fig. 1) The thickness of the plank will
determine the space between the stairs
and the bottom rail.
place the bottom rail, baluster routs
facing up, on the plank with the label
reading “This end top of stair.” at the
top post. Slide the rail up or down until
the rout spacing is even on each end
(Fig. 2).
make a mark on each post to indicate
the upper surface of the bottom rail (Fig.
3).
(Fig. 1)
(Fig. 2)