RI-F100-C
OP532-
V01
PRODUCT PROFILE
96mm x 96mm
SPECIFICATIONS
I
Display
: Liquid crystal display with backlight 4 lines,
4 digits per line to show electrical Parameters
5th line, 8 digits to show energy Bar graph for
Current indication as percentage of CT rating
LCD Indications
:
- Integration of energy
PRG
- Unit is in configuration menu
- Communication in progress
- Maximum & Minimum Demand of Power
Wiring Input
: 3 Ø 4 wire
3 Ø - 4 wire
-
(Only MID approved for
)
1
1 Ø 2 wire - P
-
Rated Input Voltage
: 3x2 0/4
V
3
00
Installation Category
: III (300V L-N)
Frequency
:
Range
47...63Hz (MID approved for 50Hz)
CT Primary
:
6,000A (Programmable for any Value)
1...
CT Secondary
: 0.01...1(1.2)A (Meter Input: 330mV)
PT Primary
: 100V 600V (Programmable for any value)
...
PT Secondary
: 173 415V AC (L-L) (Programmable for any value)
...
Display Update Time : 1 sec
for all parameters
ond
Display Scrolling
: Automatic / Manual
Temperature
: Operating: -10 C 55 C
°
°
...
Storage
: -20 C 75 C
°
°
...
Humidity
: 85% non-condensing
Mounting
: Panel mounting
Meter Type
: Indoor
Weight
: 318gms
IP rating
: IP54 Front only (When fitted with rubber gasket)
Pulse Output
External
VDC max. 100mA max
:
5...27
/
.
Pulse Duration : Selectable 50...300mS
Pulse
Selectable 0.01 99.99kWh
Resolution:
...
Communications
: RS485 Modbus RTU
The meter is intended to be installed in Mechanical Environment `M1`,with
Shock and Vibrations of low significance, as per 2004/22/EC Directive.
The meter is intended to be installed in Electromagnetic Environment `E2`,
as per 2004/22/EC Directive.
SAFETY PRECAUTIONS
RESOLUTION
PT Ratio x CT Ratio
kWh
SERIAL COMMUNICATION
Interface standard and protocol
Communication address
Transmission Mode
Data types
Transmission distance
Transmission speed
Parity
Stop bits
RS
AND
485
MODBUS RTU
1 255
...
Half duplex
Float, Hex and Integer
500 Met
maximum
re
300, 600,1200, 2400, 4800, 9600,
19200 (in bps)
None, Odd, Even
1 or 2
ACCURACY
Frequency
For L-N > 20V,
For L-L > 35V
Voltage V
L-N
Voltage V
L-L
Current
±
0.5% of F.S.
±
0.5% of F.S.
±
0.5% of F.S.
±
0.1% of F.S.
100 ms
(max and independent of baud rate)
Response time
EN50470 : CI.B
-3
EN62053-23: CI.2
Active Power
Apparent power
Reactive Power
1%
1%
1%
Power factor
Active energy
Reactive energy
Apparent energy
MAX/MIN
Active Power
MAX/MIN
Reactive Power
MAX Apparent Power
±
0.01 (Digit)
1%
Class 1
1%
1%
NOTE:
Once Programming Mode Is entered The parameters
below will be locked out after 15 Minutes. No further
adjustment is possible without returning to supplier.
Network Selection
PT secondary
CT Primary
Pulse width
Pulse Duration
PT Primary
Factory default
Energy Reset
CONFIGURATION LOCK PARAMETER DESCRIPTION
Doc. name : OP INST RI-F 00 OP
-V01(Page 1 of 6)
3
300
Product
Outputs
Certification
MID
RI-F 00 -C
3
-*
RS485 (Modbus RTU) & Pulse
(F.S - Full Scale)
For the installation to be valid the following steps must
be followed:
MID APPROVAL INSTALLATION NOTES
:
RI-F300
0.01K
0.1K
1K
0.01M
0.1M
<15
<150
<1500
<15000
>15000
ORDER INFORMATION
Safety related
, symbols and instructions that appear in this
notifications
operating manual or on the equipment must be strictly followed to ensure the
safety of personnel as well as the instrument.
If the equipment is not used in a manner specified by the manufacturer it may
impair the protection provided by the equipment.
Do not use the equipment if there is any mechanical damage.
Ensure that the equipment is supplied with correct voltage.
No repairs, maintenance or adjustments are possible.
WIRING GUIDELINES
prevent
, always isolate the power supply to the
1.To
the risk of electrocution
equipment prior to undertaking any work. Always confirm absence of
supply prior to starting work using appropriate voltage detection
equipment.
2. Wiring shall be done strictly according to the terminal layout. Confirm that
before energizing the equipment
all connections are correct
.
3. Routing of connecting cables shall be away from any internal EMI source.
4 C
es
voltage and output
s
. abl
used for
connection must have a cross section
of 0.5mm to 2.5mm . (20 to14AWG ; 75 C (min) )
2
2
0
5
s
solid
. Copper cable should be used. ( tranded or
core cable)
6
be
. All wiring to
in accordance with applicable local standards
1.Read complete instructions prior to installation
operation of the unit.
or
2.Risk of electric shock. Only to be installed by competent personnel.
3.The equipment in its installed state must not come in close proximity to any
heating sources, oils, steam, caustic vapours or other unwanted process
by-products.
CAUTION
To change:
1. Press
"I" for 3 seconds
and hold
until the display changes, release the
key. Press and hold the key again for 3 seconds.
2. Wait 5 seconds for meter to resume online reading. Meter display will
show LH when checked using the
procedure described
“To check”
below.
To check:
1. Press
"I" for 3 seconds
and hold
until the display changes, release the
key.
2. Wait 5 seconds and the meter will resume normal operation.
Please note: All
easywire current transformers as default
THREE PHASE
are configured to monitor Incoming supplies (L1 is on the right-hand side
when viewed from the P2 face. If the transformer is to be used for load
monitoring (Requiring L1 to be on the Left-hand side when viewed from
the P2 face), the operator must perform the
procedure
“To change”
described below;
CT ROTATION - IMPORTANT NOTE
I
Note:
blinks every 5 sec. This indicates energy is being consumed.
Example: If CT=100/5A (CT=20) & VT=380:380 (VT=1:1, VT=1), then energy
reading resolution=0.1K (20x1=20) and a pulse will be emitted every
100wh
1. The CT ratio must be set before putting the meter
into service.
2. The RJ45 connection between the meter and the