NOZZLE CONTROL VALVE INSTALLATION
• When securing the primary and secondary boom cables on the implement, begin at the outer boom tips.
Adjust the cable position to provide sufficient slack between valve tee branches while working toward the
center of the implement.
• Route the boom cables on the inside of the boom frame work.
• Secure cables using a zip tie at each nozzle control valve tee branch, and one between each tee branch along
the cable length.
SECONDARY BOOM CABLE ROUTING AND CONNECTIONS
NOTE:
Please review the Best Practices and Recommendations section on page 16 before routing or securing
the boom cables on the implement. Do not to connect or secure the cables until instructed to do so
in the procedure.
1. Locate the terminator on each of the secondary boom cables (refer to the Kit Contents section on page 6). The
terminator may be braided over some boom cables to secure it in place.
FIGURE 3. Secondary Cable ISOBUS Powell Terminator
2. If the terminator is not braided over, verify the terminator is tightly secured to the main cable harness with a zip
tie. If the terminator is not secured, excessive stress on the wires can cause breakage and/or intermittent nozzle
CAN communication.
3. Route the secondary boom cables so the terminators are located at the outer tips of the left and right boom.
4. Starting from the mid-boom fold point, feed the terminator end of the secondary boom cable through the
boom framework. Follow the existing cable or plumbing runs and through existing cable retention devices as
appropriate.
5. If not already applied, apply a single short burst of corrosion inhibitor (Corrosion X HD (Raven P/N 222-0000-
020 or available from http://www.corrosionx.com/corrosionx-heavy-duty.html)) into the NCV connection. Be
sure the corrosion inhibitor has coated the NCV contacts and recessed portions of the connector.
NOTE:
To determine is corrosion inhibitor has been applied, inspect for a thick liquid in the bottom of the
connector
6. Once the secondary boom cable is routed appropriately, begin connecting the valve tee branches to the nozzle
control valves, starting with the nozzle control valve at the outer end of the boom.
7. At each valve branch, adjust the cable as necessary to provide slack between nozzle control valve connections.
The large round connector on the secondary boom cable should end near the fold point.
8. Repeat this procedure to route and connect the secondary boom cable on the opposite boom.
NOTE:
Route and connect the primary and secondary cables before securing the cable with the supplied zip
ties.
PRIMARY BOOM CABLE ROUTING AND CONNECTIONS
NOTE:
Do not connect or secure the cable until instructed to do so in the procedure.
Powell Active
Terminator
Содержание Hagie Hawkeye STS
Страница 1: ...Hagie Hawkeye Installation Manual P N 016 0171 635 Rev C 05 17 E29489 Copyright 2017 ...
Страница 16: ...CHAPTER 3 12 Hagie Hawkeye Installation Manual ...
Страница 18: ...CHAPTER 4 14 Hagie Hawkeye Installation Manual ...
Страница 28: ...CHAPTER 6 24 Hagie Hawkeye Installation Manual ...
Страница 40: ...CHAPTER 7 36 Hagie Hawkeye Installation Manual ...
Страница 41: ...APPENDIX A P N 016 0171 635 Rev C 37 APPENDIXASYSTEM DIAGRAM ...
Страница 42: ...APPENDIX A 38 Hagie Hawkeye Installation Manual ...
Страница 43: ...P N 016 0171 635 Rev C 39 ...
Страница 44: ...APPENDIX A 40 Hagie Hawkeye Installation Manual ...
Страница 48: ...APPENDIX B 44 Hagie Hawkeye Installation Manual ...
Страница 50: ...Index 46 Kubota M7 Series SmarTrax Installation Manual ...