Quantum ActiveScale X100 Скачать руководство пользователя страница 28

ActiveScale™ X100 Site Requirements Guide

28

2.5  Servicing space requirement

The ActiveScale X100 requires that enough space be available at the front and the rear of the system to 

install and service system components. The front space requirement is based on the length of the longest 

system component, plus the space necessary to fit a person servicing the system. The rear space 

requirements is based on space a technician would need to service all of the CRU and FRU parts at the rear 

of the unit.

Table 2

-

6. Space Requirement Specifications

Figure 2

-

1. Minimum Servicing Space Required

The following list contains other considerations that should be made for servicing the system:

• Mounting a PDU or other equipment vertically in the customer selected rack may impede the ability of 

technicians to service system components. For example, because of the position of the Storage Enclosure 

Basic fans, mounting a PDU or other equipment too close to these components could necessitate the 

removal of the PDU in order to service those parts.

2.6  Delivery route inspection

During the receiving process, the system components will need to be moved through the facility until it 

reaches the data center or computer room where the system will be installed. This section describes the 

considerations that the installation team should make before receiving the system and moving it through 

the facility.

2.6.1  Walking path inspection

Walking paths must be clear of obstructions and wide enough to allow passage of the system components 

to the site where it will be unpacked. The following is a list of obstructions to consider when conducting a 

walking path inspection:

Cables 

- Consider removing cables, including ramped cable covers, from the walking path before moving 

the pallet. Leaving the cables in place creates a safety hazard for the installation team and can damage the 

cables.

Lift Locations 

- There may be locations along the walking path where the system must be lifted in order 

to proceed. Make sure that lift equipment is available at this location on the day of the delivery.

Elevators 

- Ensure that any elevators that will be required to lift the equipment to the data center/

computer room are rated to carry the full load of the system plus passengers.

Specification

Value

Minimum Front of Rack Space

1220mm (48in.)

Minimum Rear of Rack Space

560mm (22in.)

FRONT

REAR

1220mm /

48in.

560mm /

22in.

Top of Rack

Содержание ActiveScale X100

Страница 1: ...ActiveScale X100 Site Requirements Guide 6 68842 04 Rev A with ActiveScale OS 6 1 0 software...

Страница 2: ...uantum Corporation and its affiliates in the United States and or other countries All other trademarks are the property of their respective owners Quantum specifications are subject to change TRADEMAR...

Страница 3: ...Miscellaneous requirements 18 2 3 5 Example configurations 19 2 3 5 1 3 Phase Delta 208V 24A NA Japan Input Power Configuration 19 2 3 5 2 3 Phase Delta 208V 48A NA Input Power Configuration 21 2 3 5...

Страница 4: ...ActiveScale X100 Site Requirements Guide 4...

Страница 5: ...e 2 1 Relevant System Specs for Rack Requirements 14 Table 2 2 System Power Requirements 15 Table 2 3 Component Power Measurements 15 Table 2 4 Recommended startup order 19 Table 2 5 Contents of Activ...

Страница 6: ...ActiveScale X100 Site Requirements Guide List of tables 6...

Страница 7: ...ActiveScale X100 Site Requirements Guide List of figures 7 List of figures Figure 2 1 Minimum Servicing Space Required 28...

Страница 8: ...ActiveScale X100 Site Requirements Guide List of figures 8...

Страница 9: ...pter defines the scope of this document and provides a brief overview of the system site requirements It also lists the regulatory compliance information relevant to the product Topics Scope on page 1...

Страница 10: ...with data growth and deliver on your business objectives The minimum configuration is equipped with one sled column in all six Storage Enclosure Basics and provides either 0 84 PB of data storage capa...

Страница 11: ...3 configuration typical max 4 45 5 34 kW Base 4 configuration typical max 5 1 6 02 kW Base 5 configuration typical max 5 75 6 7 kW Full Base 6 configuration typical max 6 4 7 4 kW System Expansion Nod...

Страница 12: ...column of populated sleds 19 59 22 91 KBTU h Full configuration base 6 seven columns of populated sleds 21 83 25 25 KBTU h System Expansion Node kit 1 0 665 to 0 785 KBTU hour Weight Minimum system w...

Страница 13: ...t that a user must address in order to support the installation and operation of the system Topics Airflow considerations on page 14 Rack requirements on page 14 PDU requirements for rackless systems...

Страница 14: ...ed for a base system dynamic loads if the system will be moved from its installation location and the additional Storage Sleds that might be added later if the system is scaled up Cable Management the...

Страница 15: ...onfigurations that will not provide the required amount of power in a single connection For example there could be a lower power single phase PDU where one PDU cannot provide enough power for the Acti...

Страница 16: ...configuration Locking Locking connector preferred Connector Locking Spec 5lbs force retention Protection Device Manually resettable circuit breaker Protection Compliance UL489 Protection Temperature C...

Страница 17: ...input power configuration System Mounting Requirements Can be mounted in the rear of the rack and be contained fully within the outer dimensions of the rack except for the input power cord Neither th...

Страница 18: ...is drawn that is sometimes several times its normal full load current This is called inrush current While inrush current might only last for microseconds it can still pose a risk to the system and ass...

Страница 19: ...ompatibility EMC agency of the country that the rack is installed in Environmental Operating temperature 5 55 C 2 3 5 Example configurations The following sections provide examples of PDU configuratio...

Страница 20: ...liant To NEMA L15 30P Input Plug Color Code N A Input Plug Ground Socket Position N A Input Cord Wire Gauge 10AWG or equivalent Nominal 208VAC Operating Range 200VAC 220VAC Number of Branches 3 Total...

Страница 21: ...vailable 60A Input Power Available 17 3KW Input Wire Connections 3P PE 3 Poles plus Protective Earth 4 wire Input Plug Compliant To IEC 60309 1 IEC 60309 2 Input Plug Color Code Blue rated operating v...

Страница 22: ...uency 50Hz Input Current Steady State Available 16A Europe International Input Current Peak Available 16A Input Power Available 11 0kVA at 230VAC 16Amp Input Wire Connections 4P PE 4 Poles plus Protec...

Страница 23: ...4 Input Configuration 1 Phase Nominal Input Voltage line to neutral 208VAC Input Voltage Operating Range 200VAC 240VAC Nominal Frequency 60Hz Input Current Steady State Available 24A NA derated Input...

Страница 24: ...g Number PDUs required by system including redundancy 4 Input Configuration 1 Phase Nominal Input Voltage line to neutral 230VAC Input Voltage Operating Range 220VAC 240VAC Nominal Frequency 50Hz Inpu...

Страница 25: ...talled on site Because of this it is important to be sure that enough space is available for the individuals that will build the system to work While installing system components there needs to be a m...

Страница 26: ...lbs Each Storage Enclosure Basic box Rail kit Chassis Sleds I O Module Power cables SAS cables Screws and fasteners 2 Pallet weight 250kg 550lbs Pallet Dimensions 965 x 1220 x 635mm 38 x 48 x 25in 2 x...

Страница 27: ...65lbs Each Storage Node box Rail kits Screws and fasteners Storage Node Power cables 3 x System Nodes Box weight 30kg 65lbs Each System Node box Rail kits Screws and fasteners Storage Node Power cable...

Страница 28: ...he system components will need to be moved through the facility until it reaches the data center or computer room where the system will be installed This section describes the considerations that the...

Страница 29: ...rther assistance contact the Quantum Contact Support Center Region Support Contact North America 1 800 284 5101 toll free 1 720 249 5700 EMEA 1 800 7826 8888 toll free 49 6131 324 185 Asia Pacific 800...

Отзывы: