SECTION 4 – INSTALLATION
Air proving switch/remote start-stop contacts
The Air Flow Switch MUST NOT be used
to start and stop the chiller (i.e. starting
and stopping the blower). It is intended
only as a safety switch.
The air proving switch is field wired to XTBC1 ter-
minals 13 to 14 to prevent operation of the refrigerant
circuit when the supply air blower is not operating.
If separate evaporator blowers are used with respect
to each refrigerant system in the condensing unit, then
two air proving switches (used for each blower) must
be wired in series across XTBC1 terminals 13 - 14. See
Figure 10 on page 37 and the unit wiring diagrams
Evaporator blower start contacts
For constant fan operation: Terminal block XTBC2 -
terminals 23 to 24, are normally open contacts that can
be used to switch field supplied power to provide a start
signal to the evaporator blower contactor. Contacts will
close whenever the daily schedule is programmed for
cooling. See
Figure 10 on page 37 and the unit wiring
Relief valves
Relief valves are located on both the high and low
pressure side of the piping. The high side relief valve
pressure setting is 650 psig. The low side relief valve
pressure setting is 450 psig.
High pressure cutout
A high pressure cutout is installed in the discharge pip-
ing of each system. The cutout opens at 585 psig plus
or minus 10 psig and closes at 440 psig plus or minus
25 psig.
Compressor heaters
Compressor heaters are standard on all models. If pow-
er is OFF more than two hours, the crankcase heaters
must be energized for 18 to 24 hours before restarting
a compressor. This will ensure that liquid slugging and
oil dilution does not damage the compressors on start.
Refrigerant piping
General
When the unit has been located in its final position, the
unit piping may be connected. Normal installation pre-
cautions should be observed in order to receive maxi-
mum operating efficiencies. System piping should con-
form to the YORK DX piping guide
Form 050.40-ES2
or ASHRAE refrigeration handbook guidelines. All
piping design and installation is the responsibility of
the user.
QUANTECH ASSUMES NO WARRANTY RE‑
SPONSIBILITY FOR SYSTEM OPERATION
OR FAILURES DUE TO INCORRECT PIPING,
PIPING DESIGN, CONTROL PROBLEMS, OR
LACK OF OIL RETURN.
Filter driers and sight glasses are shipped loose for field
installation on each refrigerant circuit. Field refrigerant
piping can be connected to the condensing unit.
All expansion valves, liquid line solenoid valves, and
refrigerant piping are field supplied and installed. TXV
sizing should be equal in size or slightly smaller than
the capacity of the circuit. If multiple coil sections are
utilized, a TXV for each section (sized accordingly)
must be installed.
Содержание QCC2015CEE
Страница 12: ...QUANTECH 12 Form QCC2 NM1 Issue Date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 38: ...QUANTECH 38 Form QCC2 NM1 Issue Date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 46: ...QUANTECH 46 Form QCC2 NM1 Issue Date 5 20 2021 Section 5 Technical data THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 102: ...QUANTECH 102 Form QCC2 NM1 Issue Date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 152: ...QUANTECH 152 Form QCC2 NM1 Issue Date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 171: ...QUANTECH 171 Form QCC2 NM1 Issue Date 5 20 2021 Notes...