5.2 Assembly and installation of the Chlorinsitu
®
IIa
n
User qualifications, mechanical/hydraulic installation: trained
skilled personnel, see
Chapter 1.3 ‘User qualification’
n
User qualification, electrical installation: electrical technician,
see
Chapter 1.3 ‘User qualification’ on page 8
1.
Check whether the assembly location complies with the
guidelines governing temperature, safety, space, humidity,
etc.
Specification of the assembly location
Ensure that the assembly location preferably
complies with the following conditions:
–
A dry area, which does not necessarily
have to be a separate room.
–
An area that can be locked/cordoned off
so that only authorised personnel have
access.
–
An ambient temperature of 10 ... 40 °C;
otherwise install an air conditioning
system.
–
It should be possible to install a sewage
drain and a bleed line.
An assembly drawing showing the correct
dimensions can also be produced to ensure
correct assembly. The assembly area and
position are determined using the drawings
provided. An assembly drawing for the Chlor‐
insitu
®
IIa can be found at the end of the
chapter.
2.
Clear the area in which the system is to be installed.
Check that there are no obstacles around the
system.
Provide a minimum clearance of 75 cm in
front of and at the side of the system cabinet
for maintenance purposes.
Provide a clearance of around 75 cm in front
of the brine storage tank and the optional
product storage tank.
3.
Remove all packaging from the system.
4.
Check whether the system has suffered damage during
transport or exhibits other damage. Check that the scope of
delivery is complete.
5.
Remove the securing material of the transport crate.
6.
Lift the system cabinet into its installation position.
7.
Check whether the system is upright and horizontal. Max.
deviation from the vertical of 4 mm per 100 cm.
8.
Remove the transport protection from the softener and the
product storage tank.
Installation and assembly