7. Installation and start-up
Premier Tech
35 / 64
Solido SMART
DOKK5110E 15.04.2020
7.2 Checklist BEFORE assembling the Solido SMART treatment system
Ok
1.
Is the control unit located between 10 m and 25 m away from the
treatment plant?
Is the control unit protected from rain and sun?
Is the Solido SMART cable long enough? (Alternatively: set up external
control columns next to the plant)
2.
Is a 230 V power supply plug with a 30 mA residual-current circuit breaker
available?
Is the protective earth conductor functioning?
3.
Is the treatment tank installed according to the installation instructions (soil
cover max. 120 cm above tank shoulder, the inflow and outflow correctly
positioned)?
4.
Is the DN160 shaft for removing sludge installed in accordance with the
installation instructions?
5.
Are the seals from the shaft assembly set (see chapter 7.3.1) for the
supply air hose and cable conduit set in place? Is the cable holder
installed?
6.
Is the air inlet support set in place?
Is the hose pulled into the shaft up to the red marking? (Standard hose
length 3 m, extension up to 10 m possible, max. 30 cm deep into the
ground, slope to inlet support = condensate trap!)
7.
Is(are) the pipe ventilator(s) installed in the centre of and horizontally on
the container floor?
8.
Are the lifters filled with water to prevent them from being lifted?
9.
Is sufficient space available in the shaft to receive the technology capsule?
10.
Is the outlet pipe from the building connected to the inflow on the plant,
and is the outflow of the wastewater treatment system connected to the
receiving water or seepage system?
11.
Is sufficient treatment tank aeration and deaeration provided?
(Roof deaeration or separate aeration and deaeration is required)
12.
Is a cable conduit (DN 50 with taut wire, on-site) installed for the Solido
SMART cable between the treatment plant and the control unit location?
13.
Is the chamber approximately half-filled with water?
Содержание Solido SMART
Страница 49: ...8 S40 control unit and available settings Premier Tech 49 64 Solido SMART DOKK5110E 15 04 2020...
Страница 56: ...9 Operational failures and resolving them Premier Tech 56 64 Solido SMART DOKK5110E 15 04 2020 NOTES...
Страница 60: ...10 Appendix Premier Tech 60 64 Solido SMART DOKK5110E 15 04 2020 10 4 EC declaration of conformity...