7 Commissioning
7.1
General
Danger
Commissioning may only be carried out by an approved installer.
The installer checks the tightness of pipes, the correct function of
all regulating, control and safety equipment, and measures the
combustion values. If this work is not carried out correctly, there is
a risk of considerable damage to persons, environment and
property.
7.2
Checklist for commissioning
Tab.13 Checklist for commissioning
1.
System location
2.
Customer
3.
Boiler type/Designation
4.
Serial number
5.
Characteristic gas val
ues
Wobbe index
kWh/m³
6.
Operating heating value
kWh/m³
7.
Have all pipelines and connections been checked for tightness?
□
8.
Flue gas system checked?
□
9.
Gas pipeline checked and vented?
□
10. Static pressure measured at the gas valve inlet?
mbar
11. Free wheeling of pumps checked?
□
12. Filling the heating plant
□
13. Water additives used
14. Gas flow pressure measured at full load at the gas valve inlet?
mbar
15. Gas injector pressure measured at full load at the gas valve outlet?
mbar
16. CO
2
content at low load
%
17. CO content at low load
ppm
18. CO
2
content at full load
%
19. CO content at full load
ppm
20.
Function test:
Heating mode
□
21.
Domestic water mode
□
22.
Programming:
Time /date
□
23.
Comfort setpoint heating circuit 1/2
°C
24.
Setpoint DHW
°C
25.
Automatic day time programme
Clock
26.
Heating curve checked?
□
27. Tightness of the flue system checked in operation (e.g. CO
2
test in annular gap)?
28. Customer instructed?
□
29. Documents handed over?
□
Only components tested and marked according to the respective standard have been used.
All system components have been installed according to the instruction of the manufacturers.
The whole system conforms to the standard.
To ensure the heat source operates reliably and economically for a long period, we recom
mend annual maintenance for the heat generator.
Date /signature
Company stamp
...............................
7 Commissioning
7703046 - 01 - 23072018
Paramount five 30 – 115
49
Содержание Paramount five 115
Страница 55: ...For more information see Technical data page 15 7 Commissioning 7703046 01 23072018 Paramount five 30 115 55 ...
Страница 138: ...For more information see Status page 132 State page 132 9 Settings 138 Paramount five 30 115 7703046 01 23072018 ...
Страница 150: ...Gas pressure not stable 11 Troubleshooting 150 Paramount five 30 115 7703046 01 23072018 ...