Flange Machine
Part Number 6Z8303
Installation and Setup
11
3
Installation and Setup
This section provides information for service technicians who have experience
and training in electrical and electronic equipment installation. This section
explains the procedures needed to assemble the machine. Although some tools,
such as a 3 mm Allen wrench and a crescent wrench, are necessary, the flange
machine requires no special tools or installation procedures upon its arrival.
Assembly time is approximately thirty minutes.
Preparing the Site
Transformer
A device
used to convert a current
from one voltage to
another.
The PFM-4000 Flange Machine does not require extensive site preparation. A
work area should be clean, level, structurally sound, and capable of supporting
100 pounds. Air drops and an electrical outlet for 220 VAC single phase must be
accessible. (For overseas voltage differences, a transformer is optional.) Ensure
that the flange machine has a clear work area of at least 3 feet (1 meter) around the
entire machine.
Unpacking the Flange Machine
The PFM-4000 Flange Machine consists primarily of the sewing head and the
sewing table. These are packed as separate units and are found within the same
shipping carton. Upon receipt of the flange machine, inspect it for any damage.
Record any dents, scratches, or other damage. Inspect all parts after opening the
containers. Confirm that all parts are shipped and undamaged. Report any
damaged parts to the shipping company.
To unpack the machine:
1
Open the shipping carton that contains the sewing table, and remove all
packing material found on top of and around the machine.
IMPORTANT!
Porter insures all
parcel post
packages. If a parcel post
shipment reaches you in damaged condition, contact us
immediately for instructions on filing a claim.