Polymaster ST3100 Скачать руководство пользователя страница 1

Septic Tank

1.  Select site

• 

Contact relevant authorities 

before digging to locate all 

underground cables and pipes

• 

Determine the best location of the 

tank taking into account existing 

underground services, excavation 

required, location of blackwater run and 

heights into tank and outlet fall to drain.

• 

Is the tank excavation hole far enough 

away not to impact on foundations 

and adjoining structures? Where 

no regulations exist the distance of 

the excavation from any structure 

should be a minimum of 2 times 

the depth of the excavation.

• 

Consult with a Geotechnical Engineer 

if you have any questions about 

possible influence of excavation 

on surrounding structures

• 

Must not be installed where there is 

a possibility of water table exceeding 

half the height of the tank

2.  Excavation

• 

Excavate hole according to 

dimensions of tank 

• 

Excavation slopes should be a 

minimum of 30 degrees

• 

Hole depth should be a minimum of 1675 

below finished pavement / lawn level

• 

Remove all loose soil from base of hole, 

and add 100mm of sand or crusher 

dust and compact to a firm level pad.

• 

Be aware of the safe working practice 

for working in excavated holes.

• 

Hole dimensions at the base should 

be a minimum of 200mm larger in 

width and length of the tank.

Installation Guide 

•  ST3100
•  ST4550 

CHECK FIRST...

Read this manual thoroughly to ensure 

all procedures are understood and 

materials needed are available.