1
2
3
4
5
Fig. 6:
Connecting sealing gas system
1 Flow regulator
4
Pressure gauge
2 Pressure regulating valve
5
Flow rate meter
3 Sealing gas connection
1
2
3
4
5
6
Fig. 7:
Connecting sealing gas system with nitrogen monitoring tablet
1 Solenoid valve
4
Pressure regulating valve
2 Nitrogen monitoring tablet
5
Sealing gas connection
3 Pressure gauge
6
Flow rate meter, flow rate monitor
Procedure
1. Connect the sealing gas connection to the gas supply.
– Connection size: 1/4" thread, ISO 228-1
2. Connect the electrics of the solenoid valve.
3. Connect the electrics of the flow rate monitor for the flow rate meter.
1(+)
PE
2 (-)
Fig. 8:
Connection data for the solenoid valve
● U = 24 V DC; P
max
= 8 W
● Contact: Normally closed
1(+)
2 (-)
Fig. 9:
Connection data for the flow rate monitor
Installation
23/62