Quick Reference Guide

The Sporlan 

S3C Case Control

 should be installed only by a qualified professional. All other system components 

should be supplied by Sporlan to ensure compatibility and proper operation.

1. INSTALLATION

(Reference diagram on back side). 

1.  Mount the controller in a rain-tight 

protected location using #8 sheet metal 
screws; tighten to 14-16 in-lbs. DIN rail 
may also be used as alternate mounting. 
The suggested mounting area is 6 inches 
high and 14 inches wide, depth is 3 inches.

2.  Mount the suction temperature sensor 

to the suction line after the evaporator. 
Connect the non-polarized sensor wires to 
“Coil Out” on the controller.  

Maximum 

torque on screw terminals is 3.5 in-lbs.

3.  Mount the defrost termination sensor to 

the coil. Connect the non-polarized sensor 
wires to “Def Term” on the controller.

4.  Mount the discharge air temperature sen-

sor in the appropriate location in the case. 
Connect the non-polarized sensor wires to 
“Dsch Air” on the controller.

5.  Mount the pressure transducer on the 

suction line near the suction temperature 
sensor, positioned at 12 o’clock.  Install 
the pressure transducer cable and connect 
the wires to “Pressure” on the controller. 
Black = “5V”, White = “S”, Green = “Gnd”.

Use caution when working around high voltage components.  
Safety covers should be used for personal safety on high voltage panels. 

6.  Connect the liquid line solenoid to “Sol/

Pulse” on the controller.

7.  Connect the Electronic Expansion Valve 

to “Stepper Valve” on controller. For alter-
nate valve configurations, see Bulletin 
100-50-9.1. 

8.  Install the S3C DM (display) and wire to 

the controller.

9.  Connect power supply to the controller 

and DM. Transformer requirements are 
24VDC 60VA, Class II.

2. SETUP

On initial power up, the display will show 



 and the controller will drive the stepper 

valve closed until set up is complete. Scan QR 
code below for full installation and operating 
manual.

Configure the controller using an S3C DM 
(display). Press “UP” or “DOWN” arrow on 
the display to view parameter options. Press 
“SET” to save. Press “ESC” button to back up 
one level in the menu. The set up must be 
complete prior to exiting otherwise changes 
will not be saved.

1.  Is the case self contained (



): Select 



, then press SET

2. Set 



, Case Identifier

3. Set 



, Application Type:

  

 (Walk In Cooler/Freezer)

  

 (Single Temperature)

  

 (Dual Temperature)

4.   Set 



, Stepper Configuration:

  

 (Electronic Pressure Regulator) 

  

 (Electronic Expansion Valve)

  

 (Use for TEV)

5. Set 



, Expansion Valve Type:

      1



     
      1

Temperature sensor should be mounted at 

either 4 or 8 o’clock, on a free-draining line.

Sporlan S3C Case Control 

Installation and Operation Manual

SD-429 / 32022

6. Set 



, Number of Evaporators

7.  Will case be integrated to a 



, Building 

Automation System; 



 or 



8. Set 



, Building Automation Protocol 

(skipped if no BAS):

  

 (MODBUS over RS-485)

  

 (BACnet over RS-485)

  

 (BACnet over IP)

  

 (MODBUS over IP) 

9. Set 



, Month

10. Set

 

, Day

11. Set

 

, Year

12. Set

 

, Time (24hr format)

13. Set 



, Refrigerant Type

14. Set 



, System EPR Type

15. Set 



, Discharge Air Setpoint

16. Set 



, Defrost Type

  

, Hot Gas

  

, Electric

  

, Air

17. Set 



, Defrost Termination 

Temperature

18. Set 



, Defrost Termination Failsafe 

Time

19. Set 



, Defrost Per Day

For detailed instructions and part numbers,

scan this QR code or go to 

solutions.parker.com/literature-100

and download 

Bulletin 100-50-9.1

.