SMARTZONE UPS INSTALLATION MANUAL
58
Figure 71: Example of a System with 2 EBP Units Connected
4. Power up the system:
a. After all electrical connections have been made the system may be powered up.
i. Ensure all breakers in the system are turned on.
1. Power ON all breakers on the back of each EBP in the system.
Note:
All EBP units have a single breaker on the back of the unit,
this breaker must be powered on for the EBP to function in the
system.
2. Power ON all UPS output breakers, refer to the appropriate
SmartZone 5-20kVA UPS User Manual for the location of the
input breaker on each UPS unit.
3. Power ON all UPS input breakers, refer to the appropriate
SmartZone 5-20kVA UPS User Manual for the location of the
input breaker on each UPS unit.
ii. Remove the lock out tag out from the breaker panel and turn ON the
panel breaker(s) for the UPS system.
iii. The system should start to power up, refer to the appropriate SmartZone
5-20kVA UPS User Manual to properly configure the system for use.
Parallel Mode System Configuration with 3-Phase or Single-Phase
Output
This section provides the electrical connections for two or more UPS units in a Parallel
Mode System with a 3-Phase input and a 3-Phase or a Single-Phase Output.